Agenda item


Land to Rear of Gracewell Care Home, Gardner Way, Adderbury

Decision:

Approved in line with the officer recommendation, subject to conditions and S106 legal agreement, details to be set out in the minutes.

Minutes:

The Committee considered application 21/01966/F for the erection of 18 dwellings and an access road at land to rear of Gracewell Care Home, Gardner Way, Adderbury for Malvern Homes Limited.

 

Councillor Rob Pattenden addressed the Committee as Local Ward Member.

 

Dianne Bratt, Chairman of Adderbury Parish Council, addressed the committee in objection to the application.

 

David Rahul, the applicant, addressed the committee in support to the application.

 

In reaching its decision the Committee considered the officers’ report and presentation, the address of the public speaker and written updates.

 

Resolved

 

(1)      That. in line with the officer’s recommendation, application 22/00747/OUT, be approved and authority be delegated to the Assistant Director for Planning and Development to grant permission, subject to

 

a)          The conditions set out below (and any amendments to those conditions as deemed necessary) and

 

b)          The completion of a planning obligation under section 106 of the town and country planning act 1990, as substituted by the Planning and Compensation Act 1991, to secure necessary mitigation as set out in the annex to the Minutes, as set out in the Minute book (and any amendments deemed necessary)

 

Conditions

 

1.         The development hereby permitted shall be begun before the expiration of three years from the date of this permission.  

 

Reason: To comply with the provisions of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

2.         The development shall not be carried out otherwise than in complete accordance with the approved plans reference SLP1, 03, 05, received 04/06/2021 revised plans reference 01 Rev A, 02 Rev A, 03 Rev A, 04, 06 rev B, 07 Rev A, 08 Rev A, 09, 10, 11 Rev A, 12 Rev A, 14, 15 received 09/09/2022 unless a non-material or minor material amendment is approved by the Local Planning Authority under the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).  

 

Reason: To clarify the permission and for the avoidance of doubt.  

 

3.         No development shall take place until the applicant (or their agents or successors in title) has submitted to and had approved in writing by the local planning authority a programme of archaeological work consisting of a written scheme of investigation and a timetable for that work.  The development shall thereafter proceed in accordance with the approved written scheme of investigation and timetable.  

 

Reason: To secure the provision of archaeological investigation and the subsequent recording of the remains, to comply with Government advice in the National Planning Policy Framework (NPPF) (Section 16). This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme. 

 

4.         Following the approval of the Written Scheme of Investigation referred to in condition 3, and prior to the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority within two years of the completion of the archaeological fieldwork.  

 

Reason: To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with the NPPF.

 

5.         No development shall commence unless and until a detailed surface water drainage scheme for the site has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be subsequently implemented in accordance with the approved details prior to the first occupation of the development. The scheme shall include:

·           A compliance report to demonstrate how the scheme complies with the "Local Standards and Guidance for Surface Water Drainage on Major Development in Oxfordshire";

·           Full drainage calculations for all events up to and including the 1 in 100 year plus 40% climate change and 10% urban creep (Note: the Cv values should be set to 0.95 and MADD should be 0.0);

·           A Flood Exceedance Conveyance Plan;

·           Comprehensive infiltration testing across the site to BRE DG 365;

·           Detailed design drainage layout drawings of the SuDS proposals including crosssection details;

·           Detailed maintenance management plan in accordance with Section 32 of CIRIA C753 including maintenance schedules for each drainage element;

·           Details of how water quality will be managed during construction and post development in perpetuity; and

·           Consent for any connections into third party drainage systems  

 

Reason: To ensure that there is no flooding due to the site drainage and that the water environment is protected and in accordance with Policies ESD6 and ESD7  of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework.

 

6.         Prior to the first occupation of the development a record of the installed SuDS and site wide drainage scheme shall be submitted to and approved in writing by the Local Planning Authority for deposit with the Lead Local Flood Authority Asset Register. The details shall include:

 

·         As built plans in both .pdf and .shp file format;

·         Photographs to document each key stage of the drainage system when installed on site;

·         Photographs to document the completed installation of the drainage structures on site;

·         The name and contact details of any appointed management company information.  

 

Reason: In accordance with section 21 of the Flood and Water Management Act 2010 and Government guidance contained within the National Planning Policy Framework.

 

7.         A schedule of materials and finishes to be used in the external walls and roof(s) of the dwelling(s) shall be submitted to and approved in writing by the Local Planning Authority prior to commencement of those works. The development shall thereafter be carried out in accordance with the approved details and shall be retained as such thereafter.

 

Reason: To ensure that the materials are appropriate to the appearance of the locality and to ensure the satisfactory appearance of the completed development in accordance with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policy C28 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

8.         No development shall commence unless and until a report has been submitted to and approved in writing by the local planning authority that demonstrates all habitable rooms within the dwellings will achieve the noise levels specified in BS8233:2014 (Guidance on sound insulation and noise reduction for buildings) for indoor and external noise levels (if required, then the methods for rating noise in BS4142:2014 should be used, such as for noise from industrial sources). Thereafter, and prior to the first occupation of the dwellings affected by this condition, the dwellings shall be insulated and maintained in accordance with approved details. 

 

Reason: To avoid noise giving rise to significant adverse impacts on health and quality of life and to comply with advice in the NPPF (section 15) and Saved Policy ENV1 of the Cherwell Local Plan 1996.

 

9.         No development shall take place, including any works of demolition until a Construction Method Statement has been submitted to, and approved in writing by the Local Planning Authority. The statement shall provide for at a minimum:

 

a.    The parking of vehicles of site operatives and visitors;

b.    The routeing of HGVs to and from the site; 

c.    Loading and unloading of plant and materials;

d.    Storage of plant and materials used in constructing the development;

e.    The erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate;

f.     Wheel washing facilities including type of operation (automated, water recycling etc) and road sweeping;

g.    Measures to control the emission of dust and dirt during construction;

h.    A scheme for recycling/ disposing of waste resulting from demolition and construction works;

i.      Delivery, demolition and construction working hours;   The approved Construction Method Statement shall be adhered to throughout the construction period for the development.   

 

Reason: To ensure the environment is protected during construction in accordance with Saved Policy ENV1 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

10.      No part of the development hereby permitted shall take place until a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model has been carried out by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and has been submitted to and approved in writing by the Local Planning Authority. No development shall take place until the Local Planning Authority has given its written approval that it is satisfied that no potential risk from contamination has been identified. 

 

Reason:  To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

11.      If a potential risk from contamination is identified as a result of the work carried out under condition 11, prior to the commencement of the development hereby permitted a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and to inform the remediation strategy proposals shall be documented as a report undertaken by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development shall take place unless the Local Planning Authority has given its written approval that it is satisfied that the risk from contamination has been adequately characterised as required by this condition.

 

Reason: To ensure that any ground and water contamination is adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

12.      If contamination is found by undertaking the work carried out under condition 10, prior to the commencement of the development hereby permitted a scheme of remediation and/or monitoring to ensure the site is suitable for its proposed use shall be prepared by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development shall take place until the Local Planning Authority has given its written approval of the scheme of remediation and/or monitoring required by this condition.

 

Reason:  To ensure that any ground and water contamination is adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

13.      If, during development, contamination not previously identified is found to be present at the site, no further development shall be carried out until full details of a remediation strategy detailing how the unsuspected contamination shall be dealt with has been submitted to and approved in writing by the Local Planning Authority. Thereafter the remediation strategy shall be carried out in accordance with the approved details.  

 

Reason: To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework.

 

14.      Prior to the first occupation of any of the dwellings hereby approved, all of the estate roads and footpaths (except for the final surfacing thereof) shall be laid out, constructed, lit and drained in accordance with Oxfordshire County Council's ‘Conditions and Specifications for the Construction of Roads’ and its subsequent amendments.  

 

Reason: In the interests of highway safety, to ensure a satisfactory standard of construction and layout for the development and to comply with Government guidance contained within the National Planning Policy Framework. 

 

15.      A plan detailing the proposed parking and turning provision for vehicles to be accommodated within the site (including details of the proposed surfacing and drainage of the provision), shall be submitted to and approved in writing by the Local Planning Authority prior to commencement of those works. The approved parking and turning facilities shall be laid out and completed in accordance with the approved details before the first occupation of the dwellings.  The car parking and turning spaces shall be retained for the parking turning of vehicles at all times thereafter.

 

Reason: In the interests of highway safety, to ensure the provision of adequate offstreet car parking and turning and to comply with Government guidance in Section 12 of the National Planning Policy Framework.

 

16.      Details of a turning area to be provided within the site so that motor vehicles may enter, turn around and leave in a forward direction including refuse and emergency service vehicles (including surfacing and drainage details) shall be submitted to and approved in writing by the Local Planning Authority before the development reaches slab level. The turning area shall be constructed and completed in accordance with the approved details before the development is first occupied and shall be retained for the manoeuvring of motor vehicles at all times thereafter.  

 

Reason: In the interests of highway safety and to comply with Government guidance in Section 12 of the National Planning Policy Framework.

 

17.      Prior to the first use or occupation of the development hereby permitted, covered cycle parking facilities shall be provided on the site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority.  The covered cycle parking facilities so provided shall thereafter be permanently retained and maintained for the parking of cycles in connection with the development. 

 

Reason:  In the interests of promoting sustainable transport modes in accordance with Government advice in the National Planning Policy Framework. 

 

18.      Prior to the first occupation of the development a Residential Travel Plan and Residential Travel Information Pack shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the approved Travel Plan Statement shall be implemented and operated in accordance with the approved details.   

 

Reason: In the interests of sustainability, to ensure a satisfactory form of development and to comply with Government guidance contained within the National Planning Policy Framework. 

 

19.      No temporary obstructions including any materials, plant, temporary structures or excavations of any kind shall be deposited / undertaken on or adjacent to the public right of way that may obstruct or dissuade the public from using the public right of way whilst the development takes place.

 

Reason: To ensure the public right of way remains available and convenient for public use.

 

20.      No development shall commence unless and until full details of the tree protection measures for all trees and hedges to be retained have been submitted to and approved in writing by the Local Planning Authority. These measures shall be set out in a detailed Arboricultural Method Statement to include the specification of the location and type of protective fencing, the timings for the erection and removal of the protective fencing, the details of any hard surfacing and underground services proposed within the root protection areas, all to be in accordance with the British Standard for Trees in Relation to Construction 5837: 2012, and the monitoring of tree protection measures during construction. All tree protective measures shall be carried out as set out in the approved Arboricultural Method Statement. 

 

Reason: To protect the visual amenity of the area in accordance with policies.

 

21.      No development above slab level shall be carried out until a lighting scheme has been submitted to and approved in writing by the Local Planning Authority. The approved lighting scheme shall be implemented in full compliance prior to the first occupation on the site.  

 

Reason: To protect the amenities of nearby residents, visual amenity and to comply with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policies C28 and C30 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

22.      A scheme for landscaping the site shall be provided to and approved in writing by the Local Planning Authority which shall include:-

(a)  details of the proposed tree and shrub planting including their species, number, sizes and positions, together with grass seeded/turfed areas and written specifications (including cultivation and other operations associated with plant and grass establishment i.e. depth of topsoil, mulch etc),

(b)  details of the existing trees and hedgerows to be retained as well as those to be felled, including existing and proposed soil levels at the base of each tree/hedgerow and the minimum distance between the base of the tree and the nearest edge of any excavation,

(c)  details of the hard landscaping including hard surface areas, pavements, pedestrian areas and steps. 

 

The development shall be carried out in strict accordance with the approved landscaping scheme and the hard landscape elements shall be carried out prior to the first occupation/use of the development and shall be retained as such thereafter. 

 

Reason: To ensure that a satisfactory landscape scheme is provided in the interest of well planned development and visual amenity and to accord with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policy C28 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

23.      All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in accordance with BS 4428:1989 Code of Practice for general landscape operations (excluding hard surfaces), or the most up to date and current British Standard, in the first planting and seeding seasons following the occupation of the building(s) or on the completion of the development, whichever is the sooner. Any trees, herbaceous planting and shrubs which, within a period of five years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the current/next planting season with others of similar size and species.

 

Reason – In the interests of the visual amenities of the area, to ensure the creation of a pleasant environment for the development and to comply with Policy ESD15 of the Cherwell Local Plan 2011-2031 Part 1, saved Policy C28 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

24.      Prior to first occupation of the development hereby approved a Landscape and Ecology Management Plan (LEMP) shall be submitted to and approved in writing by the Local Planning Authority. The development shall not be carried out other than in accordance with the approved details.   

 

Reason: To protect habitats of importance to biodiversity conservation from any loss or damage in accordance with Policy ESD10 of the Cherwell Local Plan 2011 – 2031 Part 1 and Government guidance contained within Section 15 of the National Planning Policy Framework.

 

25.      No development shall take place (including demolition, ground works, vegetation clearance) until a Construction Environmental Management Plan (CEMP: Biodiversity) has been submitted to and approved in writing by the Local Planning Authority. The CEMP: Biodiversity shall include as a minimum:

 

(a)  Risk assessment of potentially damaging construction activities;

(b)  Identification of ‘Biodiversity Protection Zones’;

(c)  Practical measures (both physical measures and sensitive working practices) to avoid or reduce impacts during construction (may be provided as a set of method statements);

(d)  The location and timing of sensitive works to avoid harm to biodiversity features;

(e)  The times during construction when specialist ecologists need to be present on site to oversee works;

(f)   Responsible persons and lines of communication;

(g)  The role and responsibilities on site of an ecological clerk of works (ECoW) or similarly competent person;

(h)  Use of protective fences, exclusion barriers and warning signs

 

The approved CEMP: Biodiversity shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the Local Planning Authority.  

 

Reason: To protect habitats of importance to biodiversity conservation from any loss or damage in accordance with Policy ESD10 of the Cherwell Local Plan 2011 – 2031 Part 1 and Government guidance contained within Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.  

 

26.      Full details of the siting, appearance and colour of any electricity or gas supply meter housings to be located on the external elevations of the buildings shall be submitted  to and approved by the Local Planning Authority prior to the construction of the building above slab level.  The development shall thereafter be carried out in accordance with the approved details.

 

Reason:  In order to safeguard the visual amenities of the area in accordance with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policy C28 of the Cherwell Local Plan 1996. 

 

27.      Notwithstanding the provisions of Class A of Part 1, Schedule 2 of the Town and Country Planning (General Permitted Development) Order 1995 (as amended) (or in any provision equivalent to that class in any statutory instrument revoking, amending or re-enacting that order), the garage(s) shown on the approved plans shall be retained for the garaging of private motor vehicles and shall not be converted to provide additional living accommodation without the grant of further specific planning permission from the Local Planning Authority. 

 

Reason: In the interests of highway safety, to ensure the provision of adequate offstreet car parking to comply with Government guidance in Section 12 of the National Planning Policy Framework.

 

28.      Notwithstanding the provisions of Classes A-D (inc) of Part 1 of Schedule 2 of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking or re-enacting or amending that order) no enlargement alteration or improvement of any dwellinghouse shall be undertaken at any time without the grant of further specific planning permission from the Local Planning Authority. 

 

Reason: Taking into account the density of the site it is considered to be in the public interest to ensure the merits of future proposals can be assessed by the Local Planning Authority so that the amenities of the adjoining occupier(s) are not adversely affected in accordance with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policies C28 and C30 of the Cherwell Local Plan 1996 and Section 12 of the National Planning Policy Framework.

 

29.      The first-floor window in the east elevation of plot 9 shall be obscure glazed, using manufactured obscure glass, (not an applied adhesive film) before the dwelling is first occupied and shall be permanently retained as such thereafter. The window shall also be non-opening, unless those parts which can be opened are more than 1.7m above the floor of the room in which it is installed and shall be permanently retained as such thereafter.

 

Reason: To ensure that the amenities of the adjoining occupier(s) are not adversely affected by loss of privacy in accordance with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policies C28 and C30 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

30.      Full details of the enclosures along all boundaries and within the site shall be submitted to and approved in writing by the Local Planning Authority prior to the commencement of those works. Such approved means of enclosure, in respect of those dwellings which are intended to be screened, shall be erected prior to the first occupation of those dwellings and shall be retained as such thereafter. 

 

Reason: To ensure the satisfactory appearance of the completed development, to safeguard the privacy of the occupants of the existing and proposed dwellings and to comply with Policy ESD15 of the Cherwell Local Plan 2011 – 2031 Part 1, Saved Policies C28 and C30 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. 

 

31.      Prior to the first occupation of the development hereby permitted, written confirmation that the development achieves a water efficiency limit of 110 litres/person/day under Part G of the Building Regulations shall be submitted to and approved in writing by the Local Planning Authority. 

 

Reason: Cherwell District is in an area of water stress, to mitigate the impacts of climate change and in the interests of sustainability, to comply with Policies ESD1 and ESD3 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance in the National Planning Policy Framework.

Supporting documents: