18 Sport Centre Modernisation - End of Project Appraisal PDF 79 KB
Report of Strategic Director, Environment and Community
Summary
To provide an end of project report for the Sport Centre Modernisation Programme.
Recommendations
(1) To note the end of project report and the positive outcomes that have already been achieved.
(2) To agree that the capital under spend be returned to reserves.
Additional documents:
Decision:
Recommendations Approved
Minutes:
The Strategic Director, Environment and Community submitted a report to provide an end of project report for the Sport Centre Modernisation Programme.
Resolved
(1) That the end of project report and the positive outcomes that have already been achieved be noted.
(2) That it be agreed that the capital under spend be returned to reserves.
Reasons
The Executive received a Sport Centre Modernisation report in November 2008 detailing the financial position. This report serves as an end of project report and appraisal and details the outcomes and objectives achieved.
Options
Option One |
To note the report and determine what action should be taken with regard to the capital under spend.
|
Option Two |
To explore reinvesting some of the under spend in the leisure centres as a means of spend to save and/or improving energy efficiency. |