Unit D1 Graven Hill Circular Road Ambrosden

Meeting: 08/12/2022 - Planning Committee (Item 97)

97 Unit D1 Graven Hill Circular Road Ambrosden pdf icon PDF 2 MB

Additional documents:

Decision:

Approved, conditions to be set out in the minutes

Minutes:

The Committee considered application 22/01829/OUT, an outline (fixing ‘Access’ only) application for the redevelopment of Graven Hill D1 Site, including demolition of existing buildings, development of B8 ‘Storage or Distribution’ use comprising up to 104,008 sq. m (GIA), creation of open space and associated highway works, ground works, sustainable drainage systems, services infrastructure and associated works at Unit D1, Graven Hill, Circular Road, Ambrosden for Graven Hill Purchaser Ltd (c/o Resolute Property Consultancy Ltd).

 

Mark Humphreys, agent for the application and Ben Taylor, from the Trust for Oxfordshire Environment addressed the committee in support of the application.

 

In reaching its decision the Committee considered the officers report, presentation, the written update, and addresses from the public speakers.

 

Resolved

 

(1)                  That the authority be delegated to the Assistant Director – Planning and Development to grant permission subject to:

 

i)               The expiry of the current consultation period on 5 December 2022 and confirmation that at the close of this consultation period, no responses have been received raising new material issues which, in the view of the Assistant Director, have not been dealt with in the assessment of the application.

And subject to

ii)              The conditions set out below (and any amendments to those conditions as deemed necessary); and

iii)            The completion of a planning obligation under section 106 of the town and country planning act 1990, as substituted by the planning and compensation act 1991, to secure the following heads of terms set out in the annex to the Minutes, as set out in the Minute book (and any amendments to those conditions as deemed necessary)

Conditions

 

Time Limits and General Implementation Conditions

1.      Application for approval of all the reserved matters shall be made to the Local Planning Authority before the expiration of three years from the date of this permission and the development hereby permitted shall be begun either before the expiration of five years from the date of this permission or before the expiration of two years from the date of approval of the last of the reserved matters to be approved, whichever is the later.

 

Reason: To comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 3(1) of the Town and Country Planning (General Development Procedure) Order 1995 (as amended).

 

2.      Details of the layout, scale, appearance and landscaping (hereafter referred to as 'the reserved matters') for each phase shall be submitted to and approved in writing by the Local Planning Authority before construction of that phase takes place and the development shall be carried out as approved.

 

Reason: To comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 6 of the Town and Country Planning (Development Management Procedure) (England) Order 2015.

 

3.      The development shall not be carried out otherwise than in complete accordance with  ...  view the full minutes text for item 97