Report of Commercial Director
Purpose of report
To report the urgent action taken by the Commercial Director in consultation with the Leader which related to the approval of a new contract sum of £2,686,299 to include £78,000 for additional fees associated with the London Housing Consortium (LHC) levy to be applied to Coach House Mews, Bicester and Lincoln Close, Banbury.
Recommendation
The meeting is recommended:
1.1 To note the urgent action taken by the Commercial Director in consultation with the Leader of the Council, which related to the approval of a new contract sum of £2,686,299 to include £78,000 for additional fees associated with the London Housing Consortium (LHC) levy to be applied to both the Coach House Mews, Bicester and Lincoln Close, Banbury housing developments.
Additional documents:
Decision:
Resolved
(1) That the urgent action taken by the Commercial Director in consultation with the Leader of the Council, which related to the approval of a new contract sum of £2,686,299 to include £78,000 for additional fees associated with the London Housing Consortium (LHC) levy to be applied to both the Coach House Mews, Bicester and Lincoln Close, Banbury housing developments be noted.
Minutes:
The Commercial Director submitted a report to report the urgent action taken by the Commercial Director in consultation with the Leader which related to the approval of a new contract sum of £2,686,299 to include £78,000 for additional fees associated with the London Housing Consortium (LHC) levy to be applied to Coach House Mews, Bicester and Lincoln Close, Banbury.
Resolved
(1) That the urgent action taken by the Commercial Director in consultation with the Leader of the Council, which related to the approval of a new contract sum of £2,686,299 to include £78,000 for additional fees associated with the London Housing Consortium (LHC) levy to be applied to both the Coach House Mews, Bicester and Lincoln Close, Banbury housing developments be noted.
Reasons
This report confirms the urgent action taken by the Commercial Director in consultation with the Leader of the Council to approve the new contract sum for the schemes identified within this report totalling £2,686m.
Alternative options
None as this is an information report for Executive to note.