Issue - meetings


South West Bicester Sports Village Update

Meeting: 06/07/2015 - Executive (Item 19)

19 South West Bicester Sports Village Update pdf icon PDF 125 KB

Report of Director of Community and Environment

 

 

Purpose of report

 

The purpose of this report is to update the Executive with the latest project position in delivering the pavilion, car park, access requirements, floodlighting and 3G synthetic sports pitch.

 

 

Recommendations

            

The Executive is recommended to

 

1.1       Note the progress in delivering phase 2 of the Bicester Sports Village project.

 

Additional documents:

Decision:

Resolved

 

(1)          That the progress in delivering phase 2 of the Bicester Sports Village project be noted.

 

Minutes:

The Director of Community and Environment submitted a report which updated Executive on the latest project position in delivering the pavilion, car park, access requirements, floodlighting and 3G synthetic sports pitch.

 

Resolved

 

(1)          That the progress in delivering phase 2 of the Bicester Sports Village project be noted.

 

Reasons

 

The Bicester Sports Village project continues to progress with a slightly adjusted programme which moves the anticipated project completion date to summer 2016.

 

Alternative Options

 

The project has been approved and is progressing in accordance with these approvals. There are no other options being considered at this time other than proposals to remain within the approved funding envelope.