84 Bicester Sports Village Update PDF 37 KB
Report of Director of Community and Environment
Purpose of report
The purpose of this report is to update the Executive with the latest project position in delivering the pavilion, car park, access requirements, floodlighting and 3G synthetic sports pitch.
Recommendations
The meeting is recommended to:
1.1 Note the progress in delivering phase 2 of the Bicester Sports Village project.
Additional documents:
Decision:
Resolved
(1) That the progress in delivering phase 2 of the Bicester Sports Village project be noted.
Minutes:
The Director of Community and Environment submitted a report which updated the Executive with the latest project position in delivering the pavilion, car park, access requirements, floodlighting and 3G synthetic sports pitch.
Resolved
(1) That the progress in delivering phase 2 of the Bicester Sports Village project be noted.
Reasons
The Bicester Sports Village project is now being progressed in the agreed form albeit slightly later than expected. The planning application will now be presented in time for determination post May elections which moves the anticipated project completion date to early 2016.
Alternative Options
The project has been approved and is progressing in accordance with these approvals. There are no other options being considered at this time other than proposals to remain within the approved funding envelope.