South West Bicester Sports Village Bi-monthly Progress Update

Meeting: 07/07/2014 - Executive (Item 27)

27 South West Bicester Sports Village Bi-monthly Progress Update pdf icon PDF 147 KB

Report of Head of Community Services

 

Purpose of report

 

To provide a progress report on the Bicester Sports Village project.

 

Recommendations

            

The meeting is recommended:

 

 1.1        To note the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping, the initial design work for Phases 2 (Pavilion and Car Park) and Phase 3 (Athletics Facility, 3G Synthetic Pitch, Tennis Courts and Floodlighting).

1.2       To commit to the next stage of the project undertake a value engineering exercise and the development of a planning application for Phase 2 and 3A.

 

Additional documents:

Decision:

Resolved

 

(1)          That the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping, the initial design work for Phases 2 (Pavilion and Car Park) and Phase 3 (Athletics Facility, 3G Synthetic Pitch, Tennis Courts and Floodlighting) be noted.

 

(2)          That the next stage of the project undertake a value engineering exercise and the development of a planning application for Phase 2 and 3A be committed to.

 

(3)          That officers be requested to liaise with Bicester Athletics Club and offer the club a meeting with the Leader, Deputy Leader and officers to update the club on the current situation.  

Minutes:

The Head of Community Services submitted a report which provided a progress report on the Bicester Sports Village project.

 

Resolved

 

(1)          That the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping, the initial design work for Phases 2 (Pavilion and Car Park) and Phase 3 (Athletics Facility, 3G Synthetic Pitch, Tennis Courts and Floodlighting) be noted.

 

(2)          That the next stage of the project undertake a value engineering exercise and the development of a planning application for Phase 2 and 3A be committed to.

 

(3)          That officers be requested to liaise with Bicester Athletics Club and offer the club a meeting with the Leader, Deputy Leader and officers to update the club on the current situation. 

 

Reasons

 

Construction of Phase 1 is on target for completion in November 2014 and pitches will be available to play on from September 2015.

 

The initial design work for Phase 2 has produced an outline cost plan which exceeds the available budget. However, the Design team are currently working on approaches to bring the cost within budget including a value engineering exercise and considering the options/implications of a smaller building. As the detailed design work is completed, building supplier costs are confirmed and planning conditions are known there will be more certainty to the cost plan. Officers will report the outcome of the Design Teams work to the Executive meeting in September.

 

Uncertainty with guaranteed access onto school sites and the lack of financial support for athletics has led the Project Board to reduce the scope of the planning application to just Phase 2 (pavilion and car parking) and Phase 3A (synthetic pitch and tennis courts). Phase 3B (athletics facility and multi-use games area) will be progressed when the school site is being planned and access issues have been resolved.

 

Some funding opportunities for Phase 3A facilities have been identified and will be pursued in the next available funding round.

 

The current programme for Phases 1 and 2 to be operational from September 2015 is on target however, this could be subject to change if the value engineering exercise is unable to produce the necessary cost reductions and the cost implication of a reduced building need further consideration. Revenue modelling work has been commissioned and will be reported to the next meeting.

 

Procurement documents are currently being produced to appoint a management contractor in June 2015

 

Alternative Options

 

The project has been approved and is progressing in accordance with these approvals. There are no other options being considered at this time other than proposals to remain within the approved funding envelope.