79 South West Bicester Sports Village Progress Update PDF 58 KB
Report of Head of Community Services
Purpose of Report
To provide a progress report on the Bicester Sports Village project.
Recommendations
The meeting is recommended:
1.1 To note the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping) and the appointment of a contractor to progress the design and planning application for Phase 2 (pavilion and car park) and Phase 3 (Athletics track, synthetic grass pitch, tennis courts, etc…).
Additional documents:
Decision:
Resolved
(1) That the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping) and the appointment of a contractor to progress the design and planning application for Phase 2 (pavilion and car park) and Phase 3 (Athletics track, synthetic grass pitch, tennis courts, etc…) be noted.
Minutes:
The Head of Community Services submitted a report which provided a progress report on the Bicester Sports Village project.
Resolved
(1) That the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping) and the appointment of a contractor to progress the design and planning application for Phase 2 (pavilion and car park) and Phase 3 (Athletics track, synthetic grass pitch, tennis courts, etc…) be noted.
Reasons
This is a Project Board update report to advise Executive of progress.
Alternative Options
The Project has been approved and is progressing in accordance with these approvals. There are no other Options being considered.