Purpose:

Exempt report in respect of award of tender for strip out and refurbishment works

Decisions:

The Corporate Director Resources submitted an exempt report to award the contract to undertake the strip-out and refurbishment works required to create the new office facilities at Castle Quay once the evaluation of tender submissions had been concluded

 

Resolved

 

(1)          That authority be delegated to the Assistant Director Property, in consultation with the Portfolio Holder for Finance and Resources, Monitoring Officer and S151 Officer, to award the contract to undertake the strip-out and refurbishment works required to create the new office facilities at Castle Quay once the evaluation of tender submissions has been concluded.

 

(2)          That authority be delegated to the Assistant Director Law and Governance to enter into the call off contract and associated agreements in this connection.

 

Reasons

 

Completion of the project works will enable the Council move to new offices at Castle Quay. The new offices, located in an easily accessible location, will be better suited to modern ways of working and service delivery and will help the Council reduce its carbon footprint.

 

The Scope of Works was developed following consultation with Council staff and an independent project team provided the resource and advice needed to develop and finalise the Scope of Works and prepare the tender documentation. 

 

Delegating approval to the Assistant Director Property, in consultation with the Portfolio Holder, Monitoring Officer and S151 Officer, to award the contract will enable the Council to meet its target move date. 

 

Alternative options

 

Option 1: Not make the contract award has been rejected as an option because the Council has already made the decision to move to Castle Quay and the space identified needs to be altered and fitted out to make suitable for Council operations. 

Option 2: Retender the works required with a lower specification has been rejected as an option because of the time needed to complete the exercise and which would mean the Council is not able to move to the new offices by its planned completion date.

 

Reason Key: Significant Expenditure or Savings and effect on communities in two or more wards;

Corporate Priorities : An enterprising economy with strong and vibrant local centres;

Reason No Public Access: Yes - by virtue of paragraph 3 of Schedule 12A of Local Government Act 1972

Declarations: None

Subject to Urgent Proceedings: No

Contact: Mona Walsh, Assistant Director - Property Email: mona.walsh@cherwell-dc.gov.uk Tel: 01295 221602.

Report author: Mona Walsh

Publication date: 09/07/2024

Date of decision: 08/07/2024

Decided at meeting: 08/07/2024 - Executive

Effective from: 09/07/2024