(1) That the progress on the construction of Phase 1 (grass pitches, cycle track and landscaping, the initial design work for Phases 2 (Pavilion and Car Park) and Phase 3 (Athletics Facility, 3G Synthetic Pitch, Tennis Courts and Floodlighting) be noted.
(2) That the next stage of the project undertake a value engineering exercise and the development of a planning application for Phase 2 and 3A be committed to.
(3) That officers be requested to liaise with Bicester Athletics Club and offer the club a meeting with the Leader, Deputy Leader and officers to update the club on the current situation.
Reason No Public Access: No
Declarations: None
Subject to Urgent Proceedings: No
Contact: Chris Rothwell, Head of Community Services Email: chris.rothwell@cherwellandsouthnorthants.gov.uk Tel: 0300 003 0104.
Report author: Chris Rothwell
Publication date: 08/07/2014
Date of decision: 07/07/2014
Decided at meeting: 07/07/2014 - Executive
Effective from: 12/07/2014