Additional documents:
Decision:
Approved, conditions to be set out in the minutes.
Minutes:
The Committee considered application 14/02121/OUT an outline application for a development to provide up to 1,700 residential dwellings (Class C3), a retirement village (Class C2), flexible commercial floorspace (Classes A1, A2, A3, A4, A5, B1, C1 and D1), social and community facilities (Class D1), land to accommodate one energy centre and land to accommodate one new primary school (up to 2FE) (Class D1). Such development would include provision of strategic landscape, provision of new vehicular, cycle and pedestrian access routes, infrastructure and other operations (including demolition of farm buildings on Middleton Stoney Road) at the proposed Himley Village, North West Bicester, Middleton Stoney Road, Bicester, Oxfordshire for Portfolio Property Partners Limited.
In reaching its decision the committee considered the officer’s report and presentation and the written update.
Resolved
(1) That permission be granted for application 14/02121/OUT subject to the following conditions (and any amendments to those conditions as deemed necessary – and their reordering as to the timescale for compliance):
CONDITIONS
Time Limits
1. No development shall commence on any phase until full details of the layout, scale, appearance, access and landscaping (hereafter referred to as reserved matters) for that phase have been submitted to and approved in writing by the Local Planning Authority.
Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).
2. In the case of the reserved matters, application for approval shall be made for the first residential phase of development not later than the expiration of three years beginning with the date of this permission.
Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).
3. In the case of all other reserved matters, in respect of subsequent phases, application for approval shall be made not later than the expiration of ten years beginning with the date of this permission.
Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).
4. The development to which this permission relates shall be begun not later than the expiration of two years from the approval of the first residential phase reserved matter and for all subsequent phases two years from the final approval of the reserved matters or, in the case of approval on different dates, the ... view the full minutes text for item 85