Agenda item


Proposed Himley Village, North West Bicester, Middleton Stoney Road, Bicester, Oxfordshire

Decision:

Approved, conditions to be set out in the minutes.

 

Minutes:

The Committee considered application 14/02121/OUT an outline application for a development to provide up to 1,700 residential dwellings (Class C3), a retirement village (Class C2), flexible commercial floorspace (Classes A1, A2, A3, A4, A5, B1, C1 and D1), social and community facilities (Class D1), land to accommodate one energy centre and land to accommodate one new primary school (up to 2FE) (Class D1). Such development would include provision of strategic landscape, provision of new vehicular, cycle and pedestrian access routes, infrastructure and other operations (including demolition of farm buildings on Middleton Stoney Road) at the proposed Himley Village, North West Bicester, Middleton Stoney Road, Bicester, Oxfordshire for Portfolio Property Partners Limited.

 

In reaching its decision the committee considered the officer’s report and presentation and the written update.

 

Resolved

 

(1)      That permission be granted for application 14/02121/OUT subject to the following conditions (and any amendments to those conditions as deemed necessary – and their reordering as to the timescale for compliance):

 

CONDITIONS

 

Time Limits

1.     No development shall commence on any phase until full details of the layout, scale, appearance, access and landscaping (hereafter referred to as reserved matters) for that phase have been submitted to and approved in writing by the Local Planning Authority.

 

Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).

 

2.     In the case of the reserved matters, application for approval shall be made for the first residential phase of development not later than the expiration of three years beginning with the date of this permission.

 

Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).

 

3.     In the case of all other reserved matters, in respect of subsequent phases, application for approval shall be made not later than the expiration of ten years beginning with the date of this permission.

 

Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2015 (as amended).

 

4.     The development to which this permission relates shall be begun not later than the expiration of two years from the approval of the first residential phase reserved matter and for all subsequent phases two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last reserved matters to be approved for that phase.

 

Reason - This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (Development Management Procedure) (England) Order 2010 (as amended).

 

Regulation

5.     Except where otherwise stipulated by condition, the development shall be carried out in accordance with the following plans and documents:

• Site Boundary Parameter Plan 1 (drawing number 592-PL-101 Rev B);

• Demolitions Parameter Plan 2 (drawing number 592-PL-102 Rev B);

• Land Use Parameter Plan 4 (drawing number 592-PL-103 Rev J);

•Building Heights Parameter Plan 5 (drawing number 592-PL-104 Rev H);

• Density Parameter Plan 6 (drawing number 592-PL-105 Rev G);

• Landscape Parameter Plan 3 (drawing number 592-PL-106 Rev H);

• Movement and Access Parameter Plan (drawing number 1665/75/04);

  dated 17 December 2014

•Surface Water Drainage Strategy and Flood Risk Assessment dated December 2014 and all additional correspondence relating to Drainage and Flood Risk.

 

Reason - For the avoidance of doubt, to ensure that the development is carried out only as approved by the Local Planning Authority and to comply with Government guidance contained within the National Planning Policy Framework.

 

6.     Prior to the submission of the first reserved matters application, a phasing plan covering the entire site the subject of this application, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter each reserved matters application shall refer to a phase, phases, or part thereof identified in the approved phasing plan and development shall proceed in accordance with the approved phasing.

 

Reason: To ensure the proper phased implementation of the development and associated infrastructure in accordance with Policy Bicester 1, SLE4 and INF1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

7.     No more than 1700 dwellings falling within Use Class C3 shall be constructed on the site.

 

Reason: To ensure that the significant environmental effects arising from the development are mitigated, as set out in the Environmental Statement, and sustainable development is achieved in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework.

 

8.     No more than 100 dwellings falling within Use Class C2 shall be constructed on the site.

 

Reason: To ensure that the significant environmental effects arising from the development are mitigated, as set out in the Environmental Statement, and sustainable development is achieved in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework.

 

9.    No more than a total of 8,000sqm floor space shall be provided for the mixed uses set out in Table 1 and each use shall not exceed the maximum Gross Internal Area for each specified use. These uses shall only be provided within the areas of the site annotated for ‘Other Uses’ and ‘Social/ Community’ on ‘Land Use Parameter Plan 4’ drawing number 592-PL-103 Rev J.

 

Table 1

Land Use                                                Maximum GIA (sqm)

Hotel (Class C1)                                      2,600sqm

Veterinary surgery (Class D1)                  2,000sqm

Pub/ Community (Classes A4/ D1)          400sqm

Retail (Classes A1, A2, A3, A4, A5)          700sqm

Office (Class B1)                                     1,000sqm

Health facility (Class D1)                          1,500sqm

Nursery (Class D1)                                  100sqm

Energy Centre (Sui Generis)                              375sqm

Water treatment plant (Sui Generis)         450sqm

 

The approved uses shall remain within the Use Classes set out above as specified in the Schedule to the Town and Country Planning (Use Classes) Order 1987 (or their equivalent in subsequent enactments or re-enactments) and for no other purpose(s) whatsoever.

 

Reason: To ensure that the significant environmental effects arising from the development are mitigated, as set out in the Environmental Statement, and sustainable development is achieved in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework.

 

10.   No individual Retail unit allowed for in Table 1 of condition 9 shall exceed 150m2 in gross floor internal area with the exception of a single unit up to a maximum of 300m2 which shall be for uses within Use Class A1 of the Town and Country Planning (Use Classes) Order 1987 (or their equivalent in subsequent enactments or re-enactments). If provided, the single retail unit over 150m2 for uses falling within Use Class A1 shall remain within that Use Class and it shall be used for no other Use whatsoever. Thereafter retail units shall not be amalgamated.

 

Reason: To ensure the scheme meets local retail needs in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained in the Eco Towns PPS and the National Planning Policy Framework.

 

Design

11.   Prior to the submission of the first reserved matters application (other than on the area annotated as ‘Other Uses’ on the Land Use Parameter Plan 4 drawing number 592-PL-103 Rev J where the Masterplan has been approved for that area pursuant to condition X, a site wide Masterplan and Design Code shall be submitted to and approved in writing by the Local Planning Authority. The Masterplan and Design Code shall set out the urban design approach for the site to include a regulating plan and supporting information to include;

       Details to provide continuity with adjacent development

       A detailed masterplan for the area fronting the Middleton Stoney Road annotated as ‘Other Uses’ on Land Use Parameter Plan 4 drawing number 592-PL-103 Rev J showing the location of each of the land uses

       Key approaches to deliver sustainable development that as a minimum meets the Eco Town PPS standards

       The identification of Character areas and for each, the built form and green spaces to include their key features, density, block layout and principles, structure and permeability

       Movement network and principles of streetscape including access locations, hierarchy, street type, form and design, cross sections, surface materials and landscaping, cycleways, footways, crossing points, street furniture, bus routes and stop locations

       Parking strategy including car and cycle parking standards and approach for residential and non-residential uses

       Public realm

       Building heights, scale, form, design features materials, architectural details and frontages

       Boundary treatments

       Key views, vistas, landmarks

       Landscape character, landscape types, green infrastructure, amenity spaces, public open space, play areas including their distribution, existing trees and retained hedges and biodiversity measures

       Provision and details of buffers to retained hedgerows and dark corridors for biodiversity

       Legibility and diversity of built form and landscape

       Landscape and boundary treatment principles for the buffer surrounding Himley Farm

       Drainage including sustainable urban drainage features

       Adaptability

 

All reserved matters applications shall be made and the development shall thereafter be carried out in accordance with the principles of the approved Masterplan and Design Code.

 

Reason: To secure the delivery of high quality sustainable development in accordance with Government guidance contained within the National Planning Policy Framework and Policies Bicester 1 and ESD15 of the Cherwell Local Plan Part 1 2011-2031. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

12.   Each reserved matter submission for built development shall be accompanied by details showing how Building for Life 12 has been used to inform the design process and that the scheme achieves Built for Life™.

 

Reason: To secure the delivery of high quality sustainable development in accordance with Government guidance contained within the National Planning Policy Framework and Policies Bicester 1 and ESD15 of the Cherwell Local Plan Part 1 2011-2031.

 

Dwellings

13.   Each dwelling hereby approved shall be provided with real time energy and travel information prior to its first occupation. Details of the provision for each phase shall be submitted to the Local Planning Authority and agreed in writing prior to the commencement of construction of dwellings above slab level within that phase. The devices shall thereafter be retained in operational condition.

 

Reason: To support the delivery of modal shift towards sustainable modes and create high quality, inclusive, sustainable development in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the         Eco Towns PPS and National Planning Policy Framework.

 

14.   Each reserved matters application shall be accompanied by a statement setting out how the design of buildings and the layout has taken account of future climate impacts, as identified in TSB research ‘Future Climate Change Risks for NW Bicester’, or any more recent assessment that has been published, and how the proposed development will be resilient to overheating, changing rainfall patterns and higher intensity storm events.

 

Reason: To address the impacts of climate change in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031, Government guidance contained within the Eco Towns PPS and National Planning Policy Framework.

 

15.   Each reserved matters application for a phase shall consider whether any area of that phase is subject to elevated levels of noise, principally from road traffic sources as set out in the Environmental Statement. Any dwellings that are to be constructed in any affected area within that phase shall be identified and confirmation provided that they will be designed and constructed in such a manner that they will contain elements of sound insulation that will ensure that the internal noise levels contained within BS 8233:2014 Table 4 can be achieved.

 

Reason: To ensure that properties are not subject to high levels of noise in accordance with Policies Bicester 1 and ESD15 of the Cherwell Local Plan 2011-2031, Policy ENV1 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

16.   Noise levels from any mechanical plant and the energy centre shall not exceed the noise emission limits contained within table 10.15 of the Environmental Statement. Any reserved matters submission for the energy centre or for development that will include mechanical plant shall include details of how the noise emission limits for that development will be met. 

 

Reason: To ensure that noise remains within acceptable levels in accordance with Policies Bicester 1 and ESD15 of the Cherwell Local Plan 2011-2031, Policy ENV1 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

Phase conditions

17.   No dwelling or employment building hereby permitted shall be occupied until that facility has been provided with service connections capable of supporting the provision of high speed broadband from the building to the nearest broadband service connection outside the site.

 

Reason: To facilitate information provision to homes for energy monitoring, travel and home working in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 Government guidance contained within the Eco Towns PPS and National Planning Policy Framework.

 

18.   No phase of development shall commence until a report has been submitted to and approved in writing by the Local Planning Authority outlining how carbon emissions from the construction process and embodied carbon within that phase will be minimised. The phase of development shall thereafter be carried out in accordance with the approved report.

 

Reason: To ensure the development achieves a reduced carbon footprint in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

19.   All services serving the proposed development shall be provided underground unless details of any necessary above ground service infrastructure, whether or not permitted by the Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended), have first been submitted to and approved in writing by the Local Planning Authority. Thereafter and prior to the first occupation of the development that they serve, the above ground services shall be provided on site in accordance with the approved details.

 

Reason - To ensure the satisfactory appearance of the completed development and to comply with Policy ESD15 of the Cherwell Local Plan 2011-2031, Policy C28 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

Transport

20.   No more than 500 dwellings shall be occupied until either;

• the development work to realign Howes Lane/ Lords Lane and provide a tunnel under the railway approved under 14/01968/F (or any other such planning permission which may be granted for the Strategic Link Road) has been completed and the road is open to vehicular traffic or,

• once all necessary consents and approvals are in place and there is certainty of the delivery of the work to realign Howes Lane/ Lords Land and provide a tunnel under the railway approved under 14/01968/F (or any other such planning permission which may be granted for the Strategic Link Road), a programme may be provided by the developer for the phasing of the remaining 1200 dwellings and associated infrastructure and other uses approved under this permission. This shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Local Highway Authority prior to any development beyond the first 500 dwellings.

 

Reason – Oxfordshire County Council as Highway Authority have advised that there is a need for a restriction on the quantum of development that can occur at North West Bicester prior to the opening of the Howes Lane/ Lords Lane realignment. The development identified has been agreed on the basis of expected delivery rates such that it is likely that this development, with other committed development would fall within the identified capacity in vehicular movements in advance of the Howes Lane/ Lords Lane realignment. Beyond this level of development and without the realignment, the highways impact of development over the identified capacity would be severe. A restriction on development is therefore necessary until such time that the realigned road is in place and open to vehicular traffic. In the event that there is certainty for the delivery of the realigned road, phasing of the development could be agreed to avoid severe traffic impacts and to mitigate the impact of traffic from the development in accordance with Government Guidance within the Eco Towns PPS and the National Planning Policy Framework.

 

21.   Each reserved matters application for a phase shall include full details of the means of vehicular accesses between the land and the highway, including, position, layout, construction, drainage and vision splays for development within that phase. Thereafter, the approved means of access for that phase shall be constructed and retained in accordance with the approved details.

 

Reason - In the interests of highway safety and to comply with Government guidance contained within the National Planning Policy Framework.

 

22.   Each reserved matters application for a phase shall include full details of the means of footway and cycleway links between the land, the local highway network and adjacent parcels, including, position, layout, construction, drainage, street lighting and a timetable for their provision for that phase.  Thereafter, the means of footway and cycleway links for that phase shall be constructed in accordance with the approved timetable and retained in accordance with the approved details.

 

Reason - In the interests of highway safety and to comply with Government guidance contained within the National Planning Policy Framework.

 

23.   Each reserved matter application for a phase shall be accompanied by a Travel Plan setting out how the development will enable at least 50 per cent of trips originating within the development to be made by non-car means, with the potential for this to increase over time to at least 60 per cent, in accordance with the Eco Towns PPS ET 11.2 (a). The Travel Plan shall be submitted to and agreed in writing by the Local Planning Authority prior to any occupations within the relevant phase and the actions of the Travel Plan shall thereafter be delivered in accordance with the Travel Plan.

 

Reason: To ensure sustainable travel in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS and National Planning Policy Framework.

 

Contamination

24.   Prior to the commencement of the development on any phase hereby permitted a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model shall be carried out by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and shall be submitted to and approved in writing by the Local Planning Authority. No development shall take place until the Local Planning Authority has given its written approval that it is satisfied that no potential risk from contamination has been identified.

 

Reason - To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

25.   If a potential risk from contamination is identified as a result of the work carried out under condition 27, prior to the commencement of the development hereby permitted on the relevant phase, a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and to inform the remediation strategy proposals shall be documented as a report undertaken by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development of the phase shall take place unless the Local Planning Authority has given its written approval that it is satisfied that the risk from contamination has been adequately characterised as required by this condition.

 

Reason - To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

26.   If contamination is found by undertaking the work carried out under condition 28, prior to the commencement of the development of the relevant phase hereby permitted, a scheme of remediation and/or monitoring to ensure the site is suitable for its proposed use shall be prepared by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development of the phase shall take place until the Local Planning Authority has given its written approval of the scheme of remediation and/or monitoring required by this condition.

 

Reason - To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

27.   If remedial works have been identified in condition 29, the development of the phase shall not be occupied until the remedial works have been carried out in accordance with the scheme approved under condition 29. A verification report that demonstrates the effectiveness of the remediation carried out must be submitted to and approved in writing by the Local Planning Authority.

 

Reason - To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

28.   Piling or any other foundation designs using penetrative methods within any area identified as being subject to risk from contamination shall not be permitted other than with the express written consent of the Local Planning Authority, which may be given for those parts of the site where it has been demonstrated that there is no resultant unacceptable risk to groundwater quality. The development shall be carried out in accordance with the approved details.

 

Reason: To ensure that pilling or deep foundations do not mobilise any contamination which may be present on site in order to ensure that controlled water quality is protected as required by Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the Eco Towns PPS and the National Planning Policy Framework.

 

29.   If, during development of any phase, contamination not previously identified is found to be present then no further development of that phase (unless otherwise agreed in writing with the Local Planning Authority) shall be carried out until a remediation strategy for that phase has been submitted to and approved in writing by the Local Planning Authority. The remediation strategy shall detail how this unsuspected contamination shall be dealt with and written approval from the Local Planning Authority shall be obtained. The remediation strategy shall be implemented as approved.

 

Reasons: To ensure that any unexpected contamination encountered is dealt with, such that it does not pose an unacceptable risk to controlled water quality as required by Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the Eco Towns PPS and the National Planning Policy Framework.

 

30.   The development hereby permitted shall not be commenced until such time as a pollution prevention scheme to dispose of contaminated surface water has been submitted to, and approved in writing by, the Local Planning Authority. The scheme shall be implemented as approved.

 

Reason - Run off from roads and areas associated with lorry and car parking areas may contain elevated levels of contaminants. Drainage from these areas could contaminate controlled waters. Details of the surface water drainage arrangements which outlines how any contamination risks will be mitigated is required to ensure controlled water quality is protected as required by Policy ENV12 of the Cherwell Local Plan 1996 and Government guidance contained within the Eco Towns PPS and the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

Biodiversity

31.   No development shall commence on any phase unless or until an up to date ecological survey has been undertaken to establish changes in the presence, abundance and impact on bio diversity within that phase. The survey results, together with an updated biodiversity mitigation plan and method statement shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development of the phase shall be carried out in accordance with the approved Mitigation Plan and Method Statement.

 

Reason - To ensure that the development does not cause harm to any protected species or their habitats in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

32.   The retained hedges shall have a buffer a minimum of 20m in width comprising of 10m either side of the retained hedge except where they form part of a dark corridor, as defined in the supporting documents to the NW Bicester Masterplan, where the buffers shall extend to a minimum width of 40m comprising of 20m either side of the retained hedge, and the woodlands shall have a buffer around their perimeter a minimum of 10m in width when measured from the canopy edge, all of which shall be demonstrated on the approved Masterplan/ Design Code unless otherwise agreed in writing by the Local Planning Authority. The hedge and woodland buffers shall be maintained thereafter as public open space and managed to maintain and create bio diversity.

 

Reason: To protect biodiversity and historic landscape features in accordance with Policies ESD10 and ESD15 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS and National Planning Policy Framework.

 

33.   No development shall commence on a phase until details of any existing hedgerow, or part thereof, to be removed, and proposals for creation of new compensatory hedgerow, have been submitted to and approved in writing by the Local Planning Authority. The compensatory hedgerow shall be provided in accordance with the approved details. If any tree or hedgerow shown to be retained is cut down, uprooted or destroyed or dies, another tree or hedgerow shall be planted in the same place within the following planting season and that tree shall be of such a size and species as will be first agreed in writing with the Local Planning Authority.

 

Reason: To protect biodiversity and historic landscape features in accordance with Policies ESD10 and ESD15 of the Cherwell Local Plan 2011-201 and Government guidance contained within the Eco Towns PPS and the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

34.   No development shall commence on a phase until an Arboricultural Method Statement (AMS) undertaken in accordance with BS:5837:2012 and all subsequent amendments and revisions including a scheme for the provision of protective fencing, to prevent damage during construction, for the retained hedgerows, trees, woodlands, ponds and areas of green space within that phase, has been submitted to and approved in writing by the Local Planning Authority. Thereafter, all works on the phase shall be carried out in accordance with the approved AMS with all tree protection erected prior to development commencing on that phase. If any tree or hedgerow shown to be retained is cut down, uprooted or destroyed or dies, another tree or hedgerow shall be planted in the same place within the following planting season and that tree shall be of such a size and species as will be first agreed in writing with the Local Planning Authority.

 

Reason: To protect biodiversity and historic landscape features in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS and National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

35.   No development shall commence until a Great Crested Newt mitigation strategy which includes a protection area for Newts, a minimum of 50m in circumference, around the two ponds on the site and the land between them, which shall be provided in accordance with that shown on ‘Landscape Parameter Plan 3’ drawing number 592-PL-106 Rev H, has been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved Great Crested Newt mitigation strategy. No removal of suitable aquatic and terrestrial habitat within 250m of the breeding ponds shall be carried out unless first agreed in writing by the Local Planning Authority.

 

Reason - To ensure that the development does not cause harm to any protected species or their habitats in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

36.   Prior to the submission of the first reserved matters application, a Bio Diversity Strategy for the site shall be submitted to and approved in writing by the Local Planning Authority. Each reserved matter application shall be accompanied by a statement setting out how the proposed development will contribute to achieving the Bio Diversity Strategy and net biodiversity gain. The development shall be carried out in accordance with the approved biodiversity strategy.

 

Reason: To secure net biodiversity gain in accordance with Policies Bicester 1 and ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS and National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

37.   No development shall commence on a phase until a Landscape & Habitat Management Plan (LHMP) for that phase detailing both management and monitoring proposals for green space (excluding building curtilages) has been submitted to and approved in writing by the Local Planning Authority. Thereafter the LHMP shall be implemented in accordance with the approved details.

 

Reason: To secure net biodiversity gain in accordance with Policies Bicester 1 and ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the Eco Towns PPS and National Planning Policy Framework.

 

38.   No development shall take place on any phase, including any works of demolition until a Construction Method Statement for that phase has been submitted to, and approved in writing by the Local Planning Authority. The statement shall provide for at a minimum:

a)     The parking of vehicles of site operatives and visitors;

b)     The routeing of HGVs to and from the site;

c)     A restriction on construction and delivery traffic during the peak traffic periods

d)     Loading and unloading of plant and materials;

e)     Storage of plant and materials used in constructing the development;

f)      The erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate;

g)     Wheel washing facilities/ road sweeping;

h)     Measures to control the emission of dust and dirt during construction;

i)      A scheme for recycling/ disposing of waste resulting from demolition and construction works;

j)        Delivery, demolition and construction working hours;

k)       The mitigation measures summarised at Table 5.5 and recommended at paragraphs 6.78, 7.62 – 7.79, 8.130 – 8.133, 9.91, 10.112, 12.78 – 12.80, 13.66 and 14.55 and tables 8.19 and 10.13 of the submitted Environmental Statement (December 2014)

 

The approved Construction Method Statement shall be adhered to throughout the construction period for the development.

 

Reason - To ensure the environment is protected during construction in accordance with Policy ENV1 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

39.     No development shall commence on a phase until a Soil Resources Plan that details the soils present, proposed storage locations, handling methods and locations for reuse, within that phase, has been submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved plan.

 

Reason: To ensure the soil resource is managed on site in accordance with Policy Bicester 1 of the Cherwell Local Plan 2011-2031.

 

40.   No removal of hedgerows, trees or shrubs, shall take place between the 1st March and 31st August inclusive, unless the Local Planning Authority has confirmed in writing that such works can proceed, based on the submission of a recent survey (no older than one month) that has been undertaken by a competent ecologist to assess the nesting bird activity on site, together with details of measures to protect the nesting bird interest on the site.

 

Reason - To ensure that the development does not cause harm to any protected species or their habitats in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 and Government guidance contained within the National Planning Policy Framework.

 

Archaeology

41.   Prior to any demolition on the site, the commencement of the development and any archaeological investigation, a professional archaeological organisation acceptable to the Local Planning Authority shall prepare a first stage archaeological Written Scheme of Investigation, relating to the application area, which shall be submitted to and approved in writing by the Local Planning Authority.

 

Reason - To safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

42.   Prior to any demolition on the site (other than in accordance with the agreed Written Scheme of Investigation) and prior to the commencement of the development and following the approval of the first stage Written Scheme of Investigation referred to in condition 46, a programme of archaeological evaluation, investigation and recording of the application area shall be carried out by the commissioned archaeological organisation in accordance with the approved first stage Written Scheme of Investigation and shall be submitted to and approved in writing by the Local Planning Authority. The programme shall be followed throughout the construction of the development.

 

Reason - In order to determine the extent, character and significance of the surviving remains of archaeological interest and to safeguard the recording and inspection of matters of archaeological importance on the site in accordance with Government guidance contained within the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

Drainage

43.   No part of the development hereby approved shall be occupied until confirmation has been provided that either:

 

       all water network upgrades required to accommodate the additional flows from the development have been completed; or

       a housing and infrastructure phasing plan has been agreed with Thames Water to allow additional properties to be occupied. Where a housing and infrastructure phasing plan is agreed no occupation shall take place other than in accordance with the agreed housing and infrastructure phasing plan.

 

Reason: To ensure that the water supply infrastructure has sufficient capacity to cope with the/this additional demand in accordance with Policy ESD8 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance within the Eco Towns PPS and the National Planning Policy Framework.

 

44.   Prior to the commencement of the development, a foul drainage strategy for conveyance and treatment, detailing any on and/or off site drainage works, shall be submitted to and approved by the Local Planning Authority. No discharge of foul or surface water from the site shall be accepted into the public system until the drainage works referred to in the strategy have been completed. No dwelling shall be occupied until the foul drainage has been provided in accordance with the approved strategy.

 

Reason - The development may lead to sewage flooding; to ensure that sufficient capacity is made available to treat and convey foul flows from the new development; and in order to avoid adverse environmental impact upon the community and water environment in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

45.   Prior to the submission of the first reserved matters application, a full surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydro-geological context of the development, shall have been submitted to and approved in writing by the local planning authority. The scheme shall subsequently be implemented in accordance with the approved details before the development is completed. The scheme shall also include:

       Discharge Rates

       Discharge Volumes

       Sizing of features - attenuation volume

       Infiltration in accordance with BRE365

       Detailed drainage layout with pipe numbers

       SUDS - Swales, Ponds, Permeable Paving, Filter Strips, Rain Gardens

       Network drainage calculations

       Phasing

 

Reason - To mitigate the risk of surface water flooding, protect water quality and

biodiversity on the site in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

46.   In addition to the site wide surface water drainage strategy, each reserved matters application for a phase shall be accompanied by a detailed surface water drainage scheme for that phase, to meet the flood risk, water quality, green infrastructure and biodiversity requirements of the site. The detailed surface water drainage scheme shall be in compliance with the approved Flood Risk Assessment, Surface Water Drainage Strategy and the Masterplan Surface Water Drainage Strategy and the approved site wide detailed surface water drainage strategy required under condition 49. The detailed surface water drainage scheme for that phase shall be accompanied by a maintenance plan for all drainage features, which shall include timings of the implementation of the plan, long term objectives, management responsibilities, maintenance schedules and procedures for dealing with the failure of any part of the system. No development of a phase shall commence until the detailed reserved matter surface water drainage scheme has been approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved scheme and shall be maintained in accordance with the approved scheme of maintenance thereafter and in perpetuity.

 

Reason: To mitigate the risk of surface water flooding, protect water quality and biodiversity on the site in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework. This information is required prior to commencement of any development on the appropriate phase as it is fundamental to the acceptability of the scheme.

 

47.   The residential development shall be constructed so as to meet as a minimum the higher Building Regulation standard for water consumption limited to 110 litres per person per day.

 

Reason: The site is located in an area of water stress and to comply with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

48.   No phase of employment development shall commence until details of the measures to be installed in that phase to minimise water consumption have been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details. The measures shall thereafter be retained in an operational condition.

 

Reason: The site is located in an area of water stress and to comply with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

49.   Prior to the commencement of the development, details of the strategy to work towards water neutrality, in accordance with the Eco Towns PPS shall be submitted to and approved in writing by the Local Planning Authority. Each reserved matters application shall demonstrate how it contributes to and is in accordance with the approved strategy.

 

Reason: The site is located in an area of water stress and to comply with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

Waste

50.   Prior to the occupation of any phase of the development, a waste strategy, setting targets above national standards for residual waste levels, recycling levels and landfill diversion and which identifies measures to facilitate waste reduction and recycling for commercial occupiers of that phase shall be submitted to and approved in writing by the Local Planning Authority. The waste reduction measures shall be implemented in accordance with the strategy.

 

Reason to ensure the appropriate management of waste in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

51.   Prior to the commencement of a phase, a Site Waste Management Plan, targeting zero construction waste to landfill for that phase, shall be submitted to and approved in writing by the Local Planning Authority. The approved Site Waste Management Plan shall thereafter be implemented in accordance with the approved details.

 

Reason - to ensure the appropriate management of waste in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

52.   No waste shall be brought to the site for the purpose of use within any future energy centre.

 

Reason - to ensure the appropriate management of waste in accordance with Government guidance contained within the Eco Town PPS and the National Planning Policy Framework.

 

53.   Prior to the submission of the first reserved matters application and in the event that the Design Code has not been approved, a detailed masterplan for the area fronting the Middleton Stoney Road annotated as ‘Other Uses’ on Land Use Parameter Plan 4 drawing number 592-PL-103 Rev J, shall be submitted to and approved in writing by the Local Planning Authority. The masterplan shall show the location of each of the land uses, access and parking locations, key frontage and public space conditions and landscape principles. All reserved matter applications for the area covered by the Masterplan approved by this condition X shall be made and the development shall thereafter be carried out in accordance with the principles of the approved Masterplan.

 

Reason: To ensure the creation of a high quality design for the mixed use area in accordance with Government guidance in the NPPF and Policy ESD15 of the Cherwell Local Plan Part 1 2011-2031. This information is required prior to commencement of any development as it is fundamental to the acceptability of the scheme.

 

(2)    That the completion of a planning obligation under section 106 of the Town and Country Planning Act 1990, as substituted by the Planning and Compensation Act 1991 to secure the following:

 

1        Affordable Housing

          Provide 30% affordable housing in accordance with an agreed phasing and mix.

Affordable housing to be provided by a Registered Provider.

Affordable Housing scheme to be submitted and approved prior to submission of first residential reserved matter submission identifying the distribution of the affordable housing.

Affordable housing to be delivered in clusters of no more than 15 affordable housing units unless agreed.

Nomination agreement

2        GP Surgery

          Provide financial contribution to the provision of a new GP Surgery or such other interim measure as may be required.

3        Thames Valley Police

          Provide financial contribution to neighbourhood policing

4        Community Hall & Sports Pavilion

Financial Contributions towards build cost of hall and sports pavilion south of the railway line along with other applicants south of the railway line.

Arrangements for temporary community facilities on the site to support the early residents until a permanent space is provided.

The safeguarding of land for a sports pavilion should a sports pavilion on an adjoining site not be forthcoming.

5        Community Development Worker

          Financial contribution for the provision of a community development worker(s) to deliver the creation of the new community during the build out of the site.

6        Community Development Fund

          Financial contribution to deliver community development

7        Employment and Training

          Provide employment and training action plan to include measures to ensure opportunities for local labour and businesses through the development, measures to support home working and to work with the local job club to advertise jobs created through construction on the site.

 

Delivery of specified number of construction (and related trades) apprenticeships in accordance with the number of opportunities identified through an agreed provider.

8        Primary School

          2.22ha of land at nil cost and provide school or financial contribution sufficient to provide a 1FE Primary School and funding to provide extra accommodation corresponding to the pupil generation (up to a 2 FE School). Timing to be agreed.

9        Secondary School

          Financial contribution towards the provision of secondary schools or such other interim measure as may be required.

Contribution towards school transport

10      SEN

          Provide contribution for the provision of SEN places

11      Library

          Contributions to the new Bicester library plus contribution towards core book stock.

12      Permanent Sport Pitches

          Provide land to accommodate the required sports pitches south of the railway line and make a proportionate contribution towards the capital and revenue costs of the pitches.

13      Public Open Space

          Layout the public open space and transfer it to a Management Company or to CDC with the appropriate commuted sums for maintenance in accordance with an agreed plan and phasing. If a Management Company is chosen, appropriate security around this to be secured.

14      Other Amenity space

          Maintenance sums towards woodland, hedges, swales (within areas of public open space), orchards and paths

15      Allotments

          Layout the allotments and transfer them to CDC in accordance with an agreed plan and phasing.

16      Play Areas

          Layout the NEAPs, LEAPS and LAPS and transfer to a Management Company or to CDC with the appropriate commuted sums for maintenance in accordance with an agreed plan and phasing. If a Management Company is chosen, appropriate security around this to be secured.

17      Indoor Sport

          Provide funding for the expansion of the Bicester Sports Centre

18      Green Space that could be used for a Burial Ground

          Provide contribution to the provision of a burial ground

19      Bio Diversity Off Sett

          Provide funding for off site bio diversity mitigation

20      Cultural & Wellbeing Strategy

          Provide a cultural and wellbeing strategy and action plan for delivery across the site

21      Community Management Organisation

          Provide funding for the establishment of the CMO and its activities including contributions towards the maintenance of community facilities across the site such as allotments, community farm and community buildings.

22      Waste Collection & Recycling

          Provide funding for the provision of domestic bins for waste and recycling

Provide funding for the provision of bring bank sites

23      Strategic Infrastructure

          Contributions towards the major infrastructure to serve NW Bicester including the realigned Howes Lane and tunnels and the costs related to such delivery including to Network Rail for the rights to construct the tunnels.

24      Bus Provision

          Provide funding for the provision of the bus service to serve the site in accordance with agreed phasing

25      Bus Access Scheme

          Provide or provide funding for the improvement of Bucknell Road and Field Street to facilitate bus access

26      Off Site Cycle Way Improvements

          Provide a contribution towards the following improvements;

         Off-site cycleway along Middleton Stoney Road between Howes Lane and Oxford Road. 

         Off site cycleway and traffic calming scheme on Shakespeare Drive

27      Field Path Improvements

          Fund improvements to Bridleway Bicester 9 and Bucknell 4 

28      Highway Works

          Contribution to Banbury Road B4100 roundabout improvement

Entry into a S38/ S278 agreement as necessary towards Highway Works.

Highway works to create up to two vehicular accesses off Middleton Stoney Road

Provision of bus stop laybys and pedestrian infrastructure including a link from the edge of the site to connect with the junction of Middleton Stoney Road and Howes Lane (or such part of it that is necessary)

Provision of footway/ cycle links to allow sustainable transport options in advance of surrounding development.

Facilitation of the delivery of wider site infrastructure including a bus only lane, pedestrian/ cycle links, ability to connect to other roads.

29      Village Traffic Calming

          Contribution to funding village traffic calming in Middleton Stoney

30      Travel Plan

          Provide funding for travel plan monitoring

31      Arrangements for non-residential facilities

          Including timescales for the provision of a principle retail store, ancillary retail store, other uses and arrangements for their marketing. There are also arrangements around the safeguarding of a site for a local health facility should an alternative not be provided and around provision of a nursery.

32      Monitoring

          Provide scheme of monitoring eco town standards

33      Bond/Guarantee

          Provide bond or guarantee for the delivery of the infrastructure

34      Monitoring fees

          Provide a fee for monitoring of legal agreements

35      On site internal roads/ streets

          Commuted sums for road adoption will be applicable

Agreement to secure internal roads and vehicular, bus only and pedestrian/cycle linkages to adjacent Northwest Bicester sites.

36      On-site sustainable transport initiatives

          Travel Plan co-ordinator

Electric Vehicle charging points

Car club

37      Zero Carbon

38      Requirements around building standards (i.e. BREEAM and CEEQUAL)

 

                   