Agenda item


Land For Proposed Development At Drayton Lodge Farmhouse, Warwick Road, Banbury

Decision:

Approved, subject to various requirements to be set out in the Minutes

Minutes:

The Committee considered application 18/01882/OUT, an outline application for a residential development, comprising the erection of up to 320 dwellings including affordable housing, together with a local centre of 0.5ha (providing retail and community facilities), landscaping, public open space, playing fields, allotments, access and associated infrastructure land for a proposed development at, Drayton Lodge Farmhouse, Warwick Road, Banbury for Trinity College (Bursar).

 

Chris Ferguson, the agent, addressed the committee in support of the application.

 

In reaching their decision, the Committee considered the case officer’s report and presentation, the comments from the public speaker and the written update.

 

Resolved

 

That authority be delegated to the Assistant Director for Planning and Economy to grant permission for application 18/01882/OUT, subject to:

 

i.                 the conditions set out below (and any amendments to those as deemed necessary)

 

CONDITIONS

 

Time Limit

 

1.              Time limit relating to outline

 

Compliance with Plans

 

2.              Except where otherwise stipulated by conditions attached to this permission, the development shall be carried out strictly in accordance with the following plans and documents:  to be inserted]

 

3.              Standard condition 1.9

 

4.              Standard condition 3.7 tree survey

 

5.              Standard condition 3.8 protection of trees

 

6.              Standard condition 3.10 soil levels around trees

 

7.              Thames Water recommended conditions

 

8.              Standard contamination conditions

 

9.              Archaeological conditions re Written Scheme of Investigation

 

10.           OCC transport and drainage conditions as recommended

 

11.           Ecological conditions as recommended by ecologist

 

12.           Design code

 

13.           Levels

 

14.           Soli management plan

 

15.           Management/storage and disposal of spoil

 

16.           Lighting details

 

17.           Scheme for public art

 

18.           Provision of waste and recycling bins

 

19.           Energy efficiency at 19% above building regulations

 

20.           Water efficiency limit of 110 litres per dwelling

 

21.           All utilities to be provided underground

 

22.           Protection of existing trees and hedges except where new access to Warwick road

 

23.           Non-residential buildings to meet BREAM very good

 

24.           Housing mix in accordance with Policy BSC4

 

25.           Noise mitigation measures in respect of Warwick Road

 

26.           Not more than 320 dwellings

 

ii.                the receipt of a satisfactory amended design and access statement and parameter plans

 

iii.              the completion of a planning obligation under section 106 of the Town and Country Planning Act 1990, as substituted by the Planning and Compensation Act 1991, to secure the following (and any amendments as deemed necessary):

 

a)       Provision of 30% affordable housing on site

b)       Provision of and commuted sum for open space/habitat management

provision of and commuted sum for on-site sports pitches

c)       Provision of and commuted sum for on-site allotments commuted sum for maintenance of existing trees and hedgerows on site commuted sum for SuDS maintenance provision of and commuted sum for on site play areas and equipment contribution of £267,182.98 toward off-site indoor sports facilities provision of on-site community building/retail facility and commuted sum for maintenance contribution towards community worker on site provision of on-site public art financial contribution to TVP financial contribution of £276,480 to support local primary care infrastructure additional land to south west to be kept clear of built development

d)       Payment of a financial contribution of £3,552,751 towards educational infrastructure serving the development

e)       Payment of £16,942 public transport infrastructure

f)        Payment of £2,600 traffic regulation order

g)       Payment of a financial contribution towards public transport service of £457,142.57fire payment of £113,409 strategic transport contribution

h)       Payment of the Council’s monitoring costs of £1,240. Section 278 Agreement to secure highway works

 