The Committee considered application 18/01206/OUT an outline application for the development of up to 46 dwellings including the demolition of existing buildings, structures and associated infrastructure (all matters reserved except the means of access onto Warwick Road) at Broken Furrow, Warwick Road, Banbury, OX17 1HJ for MK1 Developments LLP.

 

In reaching its decision the Committee considered the officer’s report, presentation and the written update.

 

Resolved

 

(1)  That authority be delegated to the Assistant Director for Planning and Economy to grant permission for application 18/01206/OUT subject to the following conditions (and any amendments to those conditions as deemed necessary) and the completion of a Planning obligation under Section 106 of the Town and Country Planning Act 1990, as substituted by the Planning and Compensation Act 1991, to secure the following (and any amendments as deemed necessary):

 

a) Provision of at least 30% affordable housing on site

b) Provision of and commuted sum for maintenance of open space including open space, hedgerows, trees and attenuation features

c) Provision of and commuted sum for maintenance of equipped Local Area of Play

d) Off-site outdoor sports facilities provision – £92,782

e) Off-site indoor sports facilities – £38,497,55

f) Community hall facilities - £49,023.12

g) £106 per dwelling for bins

h) Provision of 2 new pedestrian accesses up to the boundary of the site and allow public access through these points

i) £1,428.57 per dwelling to sustain and enhance the local bus service

j) £1,869 per dwelling towards ‘east west strategic movements – Warwick Road corridor’

k) Obligation to enter into a S278 agreement to secure the new access and improvements.

l) £22,873 contribution towards nursery provision

m) £364,587 contribution towards the primary school provision

n) £338,650 contribution towards secondary (incl. sixth form) provision

 

CONDITIONS

 

Time Limits

1.    No development shall commence until full details of the layout (including the layout of the internal access roads and footpaths), scale, appearance, and landscaping (hereafter referred to as reserved matters) have been submitted to and approved in writing by the Local Planning Authority.

  

Reason: This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004

 

2.    In the case of the reserved matters, the final application for approval shall be made not later than the expiration of three years beginning with the date of this permission.

 

Reason: This permission is in outline only and is granted to comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004

 

3.    Application for approval of all the reserved matters shall be made to the Local Planning Authority before the expiration of three years from the date of this permission and the development hereby permitted shall be begun either before the expiration of five years from the date of this permission or before the expiration of two years from the date of approval of the last of the reserved matters to be approved whichever is the later.

 

Reason : To comply with the provisions of Section 92 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004, and Article 5(1) of the Town and Country Planning (General Development Procedure) Order 2015 (as amended).

 

Plans

4.    Except where otherwise stipulated by conditions attached to this permission, the development shall be carried out in broad accordance with the following plans and documents: Flood Risk Assessment; Arboricultural Impact Assessment; Ecological Appraisal; Archaeological Desk-Based Assessment; Flood Risk Assessment and drainage Strategy.

 

Reason: For the avoidance of doubt, to ensure that the development is carried out only as approved by the Local Planning Authority and comply with Government guidance contained within the National Planning Policy Framework.

 

Finished floor levels

5.    No development shall take place until details of all finished floor levels in relation to existing and proposed site levels and to the adjacent buildings have been submitted to and approved in writing by the Local Planning Authority. The development hereby permitted shall be constructed strictly in accordance with the approved levels.

 

Reason: To secure an acceptable standard of development that safeguards the visual amenities of the area and the living conditions of existing and future occupiers and to ensure compliance with Policy ESD15 of the Cherwell Local Plan 2011-2031 Part 1 and government guidance within Section 12 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

Land Contamination Desk Study / Site Walkover

6.    No part of the development hereby permitted shall take place until a desk study and site walk over to identify all potential contaminative uses on site, and to inform the conceptual site model has been carried out by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and has been submitted to and approved in writing by the Local Planning Authority. No development shall take place until the Local Planning Authority has given its written approval that it is satisfied that no potential risk from contamination has been identified.

 

Reason:  To ensure that any ground and water contamination is identified and adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

Land Contamination Intrusive Investigation

7.    If a potential risk from contamination is identified as a result of the work carried out under condition 6, prior to the commencement of the development hereby permitted, a comprehensive intrusive investigation in order to characterise the type, nature and extent of contamination present, the risks to receptors and to inform the remediation strategy proposals shall be documented as a report undertaken by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development shall take place unless the Local Planning Authority has given its written approval that it is satisfied that the risk from contamination has been adequately characterised as required by this condition.

 

Reason: To ensure that any ground and water contamination is adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

Land Contamination Remediation Scheme

8.    If contamination is found by undertaking the work carried out under condition 7, prior to the commencement of the development hereby permitted, a scheme of remediation and/or monitoring to ensure the site is suitable for its proposed use shall be prepared by a competent person and in accordance with DEFRA and the Environment Agency's ‘Model Procedures for the Management of Land Contamination, CLR 11’ and submitted to and approved in writing by the Local Planning Authority. No development shall take place until the Local Planning Authority has given its written approval of the scheme of remediation and/or monitoring required by this condition.

 

Reason:  To ensure that any ground and water contamination is adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

Land Contamination Remediation Works

9.    If remedial works have been identified in condition 8, the development shall not be occupied until the remedial works have been carried out in accordance with the scheme approved under condition 8. A verification report that demonstrates the effectiveness of the remediation carried out must be submitted to and approved in writing by the Local Planning Authority.

 

Reason: To ensure that any ground and water contamination is adequately addressed to ensure the safety of the development, the environment and to ensure the site is suitable for the proposed use, to comply with Saved Policy ENV12 of the Cherwell Local Plan 1996 and Section 15 of the National Planning Policy Framework.

 

Drainage

10.  Development shall not begin until a surface water drainage scheme for the site, based on sustainable drainage principles and an assessment of the hydrological and hydro-geological context of the development, has been submitted to and approved in writing by the local planning authority. The scheme shall not be implemented other than in accordance with the approved details and shall be implemented before the development is completed. The scheme shall also include:

 

• Discharge Rates

• Discharge Volumes

• SUDS (Permeable Paving, Soakaway Tanks)

• Maintenance and management of SUDS features (To include provision of a SuDS Management and Maintenance Plan)

• Infiltration in accordance with BRE365

• Detailed drainage layout with pipe numbers

• Network drainage calculations

• Phasing

• Flood Flow Routing in exceedance conditions (To include provision of a flood exceedance route plan)

 

Reason: To ensure that sufficient capacity is made available to accommodate the new development and in order to avoid adverse environmental impact upon the community and to ensure compliance with Policy ESD 7 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance within the National Planning Policy Framework. This information is required prior to commencement of the development as it is fundamental to the acceptability of the scheme.

 

Access

11.  Prior to the commencement of the development hereby approved, full details of the means of access between the land and the highway on Warwick Road including position, layout, and vision splays shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, and prior to the first occupation of any of the development, the means of access shall be constructed and retained in accordance with the approved details. Agreed vision splays shall be kept clear of obstructions higher than 0.6m at all times.

 

Reason - In the interests of highway safety and to comply with Government guidance contained within the National Planning Policy Framework.

 

Construction Traffic Management Plan

12.  Prior to commencement of the development hereby approved, a Construction Traffic Management Plan (CTMP) shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development shall not be carried out other than in accordance with the approved CTMP.

 

Reason: In the interests of highway safety and the residential amenities of neighbouring occupiers and to comply with Government guidance contained within the National Planning Policy Framework.

 

Archaeology

13.  Prior to any demolition and the commencement of the development a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation, relating to the application site area, which shall be submitted to and approved in writing by the Local Planning Authority.

 

Reason - To safeguard the recording of archaeological matters within the site in accordance with the NPPF (2018).

 

14.  Following the approval of the Written Scheme of Investigation referred to in condition 13, and prior to any demolition on the site and the commencement of the development (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority and approved in writing.

 

Reason – To safeguard the identification, recording, analysis and archiving of heritage assets before they are lost and to advance understanding of the heritage assets in their wider context through publication and dissemination of the evidence in accordance with the NPPF.

 

Energy Statement

15.  Prior to the commencement of any works associated with the construction of a dwelling, details of the means by which all dwellings will be designed and constructed to achieve an energy performance standard equivalent to a 19% improvement in carbon reductions on 2013 Part L of the Building Regulations (unless a different standard is agreed with the local planning authority) shall be submitted to and approved in writing by the local planning authority. The development shall thereafter be carried out in accordance with the approved details and no dwelling shall be occupied until it has been constructed in accordance with the approved energy performance measures. 

 

Reason - In the interests of environmental sustainability in construction in accordance with the requirements of Policy ESD3 of the Cherwell Local Plan 2011-2031 Part 1 and government guidance in the National Planning Policy Framework.

 

Biodiversity enhancement

16.  Prior to the commencement of the development hereby approved including any demolition, and any works of site clearance, and as part of any reserved matters application for layout and landscaping, a method statement and scheme for enhancing biodiversity on site such that an overall net gain for biodiversity is achieved, to include details of enhancement features and habitats both within green spaces and integrated within the built environment, shall be submitted to and approved in writing by the Local Planning Authority.  This shall also include a timetable for provision. Thereafter, the biodiversity enhancement measures shall be carried out and retained in accordance with the approved details.

 

Reason: To ensure the development provides a net gain in biodiversity in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance contained within the National Planning Policy Framework.

 

NOTE: It is advised that this condition include a Biodiversity Impact Assessment metric to show how a clear net gain for biodiversity will be achieved.

 

Landscape and Ecological Management Plan (LEMP)

17.  Prior to the commencement of the development hereby approved, a Landscape and Ecology Management Plan (LEMP) shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development shall not be carried out other than in accordance with the approved LEMP.

 

Reason -To protect habitats of importance to biodiversity conservation from any loss or damage in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance contained within the National Planning Policy Framework.

 

Lighting strategy

18.  Prior to the installation of any external lighting a full lighting strategy to include illustration of proposed light spill and which adheres to best practice guidance, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development shall be carried out in accordance with the approved document.

 

Reason -To protect habitats of importance to biodiversity conservation from any loss or damage in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance contained within the National Planning Policy Framework.

 

Water system upgrade

19.  No properties shall be occupied until approval has been given in writing by the Local Planning Authority that either:

 

- all water network upgrades required to accommodate the additional flows from the development have been completed; or

- a housing and infrastructure phasing plan has been agreed with Thames Water and the Local Planning Authority in writing to allow additional properties to be occupied. Where a housing and infrastructure phasing plan is agreed no occupation shall take place other than in accordance with the agreed housing and infrastructure phasing plan.

 

Reason - The development may lead to no / low water pressure and network reinforcement works are anticipated to be necessary to ensure that sufficient capacity is made available to accommodate additional demand anticipated from the new development

 

Travel information packs

20.  Prior to first occupation the development a Travel Information Pack shall be submitted to and approved by the Local Planning Authority. Thereafter the first residents of each dwelling shall be provided with a copy of the approved Travel Information Pack.

 

Reason: To ensure all residents and employees are aware from the outset of the travel choices available to them, and to comply with Government guidance contained within the National Planning Policy Framework.

 

Water usage

21.  No dwelling shall be occupied until it has been constructed to ensure that it achieves a water efficiency limit of 110 litres person/day and shall continue to accord with such a limit thereafter.

 

Reason - In the interests of sustainability in accordance with the requirements of Policy ESD3 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance contained within the National Planning Policy Framework.

 

Compliance with ecological appraisal

22.  The development hereby approved shall be carried out strictly in accordance with the recommendations set out in sections MM1-MM8 and MM11-MM14 of the Ecological Appraisal carried out by Aspect Ecology dated March 2018 unless otherwise agreed in writing by the Local Planning Authority.

 

Reason - To ensure that the development does not cause harm to any protected species or their habitats in accordance with Policy ESD10 of the Cherwell Local Plan 2011-2031 Part 1 and Government guidance contained within the National Planning Policy Framework.

 

Electrical Vehicle Infrastructure

23.  Each dwelling shall be provided with ducting to allow for the future installation of electrical vehicle charging infrastructure to serve that dwelling prior to its first occupation.

 

Reason - To maximise opportunities for sustainable transport in accordance with Government guidance contained within the National Planning Policy Framework.

 

 (2)                   As the statutory determination period for application 18/01206/OUT expires on 30 June 2019, if the section 106 agreement/undertaking is not completed and the permission is not able to be issued by this date and no extension of time has been agreed between the parties, that authority be delegated to the Assistant Director for Planning and Economy to refuse the application 18/01206/OUT for the following reason:

 

1.         In the absence of the completion of a satisfactory unilateral undertaking or any other form of Section 106 legal agreement, the Local Planning Authority is not satisfied that the necessary infrastructure directly required both on and off site as a result of this development, in the interests of: safeguarding public infrastructure, education provision, community facilities and indoor and outdoor sports/recreation facilities; mitigating highway safety concerns; encouraging use of sustainable modes of transportation; delivering mixed and balanced communities by the provision of affordable housing; and securing on site future maintenance arrangements will be provided. This would be contrary to Policy INF1, PSD1, SLE4, BSC3, BSC4, BSC9, BSC10, BSC11, BSC12, Banbury 5, ESD1 and ESD15 of the Cherwell Local Plan (2011-2031) Part 1 and Government guidance contained within the National Planning Policy Framework.