To provide an update to Executive on the
progress of the Bicester Market Square project; including the
preferred concept design which is the result from the community
engagement over the last 9 months, the new estimated project
programme and estimated cost of delivery. To seek approval of the
suggested concept design and move to the next stage of the project
which includes detailed design development, submitting a planning
application & the report will also provide a recommendation for
a suggested procurement strategy for a contractor to deliver the
project.
Decision type: Key
Reason Key: Significant Expenditure or Savings and effect on communities in two or more wards;
Decision status: Recommendations Approved
Wards affected: Bicester East;
Notice of proposed decision first published: 30/05/2025
Decision due: 2 Sep 2025 by Executive
Lead member: Deputy Leader of the Council and Portfolio Holder for Finance, Property & Regeneration
Lead director: Executive Director Place & Regeneration
Department: Regeneration and Economy
Contact: Julia Harrington, Head of Regeneration and Economy Email: julia.harrington@cherwell-dc.gov.uk Tel: 07540 433310.
Reason No Public Access: No