Decision:
Approved, subject to conditions
Minutes:
The Committee considered application 12/01388/REM for reserved matters (Outline application 06/00967/OUT) construction of 21 affordable units.
In response to Members’ concerns regarding flooding, the Development Control Team Leader confirmed that comments from the Environment Agency had now been received and no objections raised.
In reaching their decision, the committee considered the officers’ report, presentation and written update.
Resolved
That application 12/01388/REMbe approved subject to the following:
(i) the receipt of satisfactory amended plans and information as requested by letter dated 13 November;
(ii) the following conditions:
(1) That except where otherwise stipulated by conditions attached to this permission, the development shall be carried out in strict accordance with the plans and documents accompanying the application; Design and Access Statement dated October 2012, Drainage Assessment; Site Investigation Report; Site Location Plan; Topographical Survey; Site Masterplan 231601/AL/P100; Drainage Strategy drawing number 12-1072-01; Landscape Management Plan 231601/AL/P106; Site Ground Floor and Levels Plan 231601/AL/P101; Site First Floor Plan 231601/AL/P102; Landscape Proposals Softworks Arrangement 231601/AL/P104; Landscape Proposals Hardworks 23160/AL/P103; Landscape Proposals Boundaries 231601/AL/P152; Landscape Proposals Hard Materials 231601/AL/P151; Proposed House Types Materials Palette 231601/AL/P150; House Type A2 231601/AL/P121 Rev A; House Type A3 231601/AL/P122; House Type B 23160/AL/P122; House Type C 231601/AL/P124; House Type D 23160/AL/P125; Cycle Store/Car Ports 231601/AL/P153; Car Ports Type 3 231601/AL/P155; Car Ports/Cycle Stores 231601/AL/P154; Street elevations 1 231601/AL/P110; Street Elevations 2 231601/AL/P111; Site Sections 231601/AL/P112; Drainage Strategy drawing number 12-1072-01; Vehicle Tracking drawing number 12-1072-05.
(2) SC2.2AA ‘paviours to be used in the construction of the roads, driveways, parking courts, private drives and footpaths’
(3) That notwithstanding the samples submitted prior to the commencement of the development further samples of bricks and tiles to be used in the construction of the walls and roofs of the dwellings and garages shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the samples so approved.
(4) (RC4A)
(5) SC2.8A ‘render’
(6) SC2.3EE ‘sample panel of artificial stone’
(7) SC3.0(a)
(8) SC3.1
(9) That notwithstanding the provisions of Class A of Part 2, Schedule 2 of the Town and Country Planning (General Permitted Development) Order 1995 and its subsequent amendments, no gate, fence, wall or any other means of enclosures, other than those agreed in accordance with this submission, shall be erected within the curtilage of any dwelling hereby approved without the prior express planning consent of the Local Planning Authority.
(10) Tree Pit details for hard and soft landscaped areas.
(11) Existing trees and hedgerows adjacent to the site to be maintained and protected during development.
(12) SC4.3(AB)
(13) SC4.6AA
(14) SC4.8AA ‘new hedge planting’
(15) SC4.9AB
(16) SC6.6AB ‘garages/car parks’
(17) Prior to the commencement of any works on site or the carrying out of any operations relating to the provision of services, full details of all service trenches, pipe runs or drains and any other excavation, earth movement or mounding required in connection with the development hereby permitted shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the details so approved.
(18) (RC73A)
(19) All agreed service trenches, pipe runs, drains or any other excavation to be constructed within the agreed Root Protection Area (RPA) of any trees on the site shall be undertaken in accordance with National Joint Utility Group (NJUG) ‘Guidelines for the Planning, Installation and maintenance of Utility Apparatus in Proximity to Trees – Volume 4 and all subsequent revisions and amendments of.
(20) (RC73A)
(21) That prior to the commencement of any development on the site, full details shall be submitted to and approved in writing by the Local Planning Authority, a scheme to prevent vehicles from being able to enter the Pingle Brook Open Space from KM21. The scheme shall be carried out in accordance with the approved details prior to the first occupation of any dwelling within KM21 and thereafter maintained in accordance with those details.
(22) That prior to the commencement of development, a scheme relating to the incorporation of Swift boxes into the built scheme shall be submitted to and approved in writing to the Local Planning Authority. The development shall be carried out in accordance with the scheme approved.
(23) Window and door details to be submitted prior to the commencement of development.
(Councillor Pickford left the meeting for the duration of this item and did not participate in the debate or vote)