Report of the Assistant Director Planning and Development.
To present a draft Housing Delivery Action Plan (HDAP) for consideration.
Recommendations
The Overview and Scrutiny Committee resolves:
1.1 To review the draft Housing Delivery Action Plan and identify any comments for consideration by the Executive at its meeting on 10 June 2025.
Decision:
Resolved:
(1) That the Housing Delivery Action Plan report be noted.
(2) That it be noted that the proposed plan requires more resource than is currently available to deliver it.
(3) That the following recommendations be submitted to the 10 June 2025 Executive meeting when it considers the Housing Delivery Action Plan:
(1) That the Executive is cognisant of the large numbers of people on the housing waiting lists.
(2) That implementation of the Housing Delivery Action Plan include prioritisation of staffing and resources.
(3) That more details on the resources to deliver the Housing Delivery Action Plan be provided by The Assistant Director - Planning and Development.
(4) That the Leader write to central Government on any delays that might be caused by delays in responses by Government departments.
(5) That suitable measures be taken to ensure that Section 106 agreements are processed on time to avoid delays.
(6) That further consideration be given to necessary infrastructure developments to deliver the Housing Delivery Action Plan.
(7) That further consideration be made to risk management of the delivery of the Housing Delivery Action Plan.
Minutes:
The Assistant Director - Planning and Development submitted a report which presented a draft Housing Delivery Action Plan (HDAP).
In introducing the report, the Portfolio Holder for Planning and Development Management and Assistant Director - Planning and Development advised that the Council's Annual Monitoring Report (AMR) 2024 had been submitted to the February 2025 meeting of the Executive. The AMR had assessed the council’s five-year housing land supply position and concluded the council could only demonstrate a 2.3-year supply, which was a shortfall of 5017 homes per annum. The position was exacerbated by the amalgamation of Oxfords unmet housing needs.
The Executive resolved that a HDAP be prepared in consultation with the Portfolio Holder for Planning and Development Management. The HDAP sought to address the housing shortfall and highlighted the need for additional resources and investment in software.
In response to a question regarding the focus on the council’s housing waiting list and whether the action plan took into account families and vulnerable people with housing needs, the Portfolio Holder for Planning and Development Management agreed that there should be a focus on the existing housing needs for the district and that a strategy had been developed to help ensure the implementation of the HDAP.
In response to a question regarding capacity of the Bicester and Oxford Sewerage works to handle the increase in demand from future housing developments, the Assistant Director - Planning and Development advised that detailed discussions had taken place with relevant stakeholders such as Thames Water and the Environment Agency who were satisfied with the proposals set out within the development plan.
In response to a question regarding the communication between utility companies and housing developers, and the role the council took aligning the two to mitigate any infrastructure issues that may occur, the Planning Policy, Conservation & Design Manager advised that relevant officers liaised with developers and infrastructure providers annually via the Infrastructure Delivery Plan (IDP) and Annual Monitoring Report, and that information was updated on an ongoing basis.
Resolved:
(1) That the Housing Delivery Action Plan report be noted.
(2) That it be noted that the proposed plan requires more resource than is currently available to deliver it.
(3) That the following recommendations be submitted to the 10 June 2025 Executive meeting when it considers the Housing Delivery Action Plan:
(1) That the Executive is cognisant of the large numbers of people on the housing waiting lists.
(2) That implementation of the Housing Delivery Action Plan include prioritisation of staffing and resources.
(3) That more details on the resources to deliver the Housing Delivery Action Plan be provided by The Assistant Director - Planning and Development.
(4) That the Leader write to central Government on any delays that might be caused by delays in responses by Government departments.
(5) That suitable measures be taken to ensure that Section 106 agreements are processed on time to avoid delays.
(6) That further consideration be given to necessary infrastructure developments to deliver the Housing Delivery Action Plan.
(7) That further consideration be made to risk management of the delivery of the Housing Delivery Action Plan.
Supporting documents: