Agenda item


OS Parcel 2200 Adjoining Oxford Road North Of Promised Land Farm, Oxford Road, Bicester

Decision:

Approved, subject to various requirements to be set out in the Minutes

Minutes:

The Committee considered application 16/02586/OUT for Phase 1 of the proposed new business park ("Bicester Gateway") comprising up to 14,972 sq m (Gross External Area) of B1 employment based buildings, plus a hotel (up to 149 bedrooms), with associated infrastructure, car parking and marketing boards for Bloombridge LLP at OS Parcel 2200 Adjoining Oxford Road North Of Promised Land Farm, Oxford Road, Bicester.

 

Richard Cutler, the applicant, addressed the committee in support of the application.

 

In reaching their decision the Committee considered the officers report, presentation and written update and address of the public speaker.

 

Resolved

 

That application 16/02586/OUT be approved, subject to the following conditions:

 

1.               No development shall commence on a phase identified within an approved phasing plan until full details of the layout, scale, appearance, access and landscaping (hereafter referred to as reserved matters) of the development proposed to take place within that phase have been submitted to and approved in writing by the Local Planning Authority. 

 

2.               Prior to the submission of any application for reserved matters approval and notwithstanding any plans submitted as part of this application, a phasing plan covering the entire application site shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be carried out in accordance with the approved phasing plan and each reserved matters application shall only be submitted in accordance with the terms of the approved phasing plan and refer to the phase it relates to as set out in the approved phasing plan.

 

3.               In the case of the reserved matters, no application for approval shall be made later than:

 

 a)       With respect to development identified as Phase 1A on drawing no.   16084 P102, the expiration of one year beginning with the date of this permission.

 

            b)         With respect to development identified as Phase 1B on drawing no. 16084 P102, the expiration of five years beginning with the date of this permission.

 

4.               Neither Phase 1A or Phase 1B of the development to which this permission relates shall be begun later than the expiration of two years from the final approval of the reserved matters relating to that phase or, in the case of approval on different dates, the final approval of the last such matter to be approved.

 

5.               Except where otherwise stipulated by condition, the development shall be carried out strictly in accordance with the following plans and drawings:16084 P101 Rev. P1

 

6.               All applications for reserved matters approval shall be accompanied by details of the existing ground levels together with proposed finished floor levels of all buildings within that phase. Development in that phase shall thereafter be undertaken in accordance with the ground/floor levels approved as part of a subsequent grant of reserved matters approval. 

 

7.               Notwithstanding any provisions contained within the Town and Country Planning (General Permitted Development Order) 2015 (and any Order or Statutory Instrument revoking, amending or re-enacting that order), all water, waste, energy and communication related services on the site to serve the proposed development shall be provided underground and retained as such thereafter except with the prior express written approval of the local planning authority.

 

8.               Except to allow for the means of access and necessary visibility splays, the existing hedgerows along the western (A41), southern and eastern (Wendlebury Road) boundaries of the site shall be retained and properly maintained at a height of not less than 3m from the date of this planning permission, and if any hedgerow plant/tree dies within five years from the completion of the development it shall be replaced and shall thereafter be properly maintained in accordance with this condition.

 

9.               All applications for reserved matters approval that submit details of ‘access’, shall be accompanied by full details of the access visibility splays relating to that phase of the development (including layout and construction). Thereafter, and prior to the first occupation of the development within that phase, the visibility splays shall be constructed in accordance with the approved details and the land and vegetation within the vision splays shall not be raised or allowed to grow above a maximum height of 0.6m above carriageway level.

 

10.            Prior to the commencement of a phase of the development, a Construction Management Plan relating to that phase shall be submitted to and approved in writing by the local planning authority which details measures to protect biodiversity during construction and mitigate impact on the local highway network. The development shall thereafter only be carried out in accordance with the approved Construction Management Plan.

 

11.            Prior to first occupation of development on a phase, a Travel Plan relating to development in that phase shall be submitted to and approved in writing by the local planning authority. Thereafter, the development in that phase shall operate in accordance with the approved Travel Plan.

 

12.            Prior to first occupation of any Class B1 development on land indicated in the application drawings as Phase 1B, a car park management plan shall be submitted to and approved in writing by the local planning authority. Thereafter, the entirety of the development on Phase 1B shall operate in accordance with the approved car park management plan.

 

13.            Prior to the first occupation of development in a phase, a delivery and servicing plan relating to that phase shall be submitted to and approved in writing by the local planning authority. Thereafter, deliveries and servicing shall thereafter take place for that phase in accordance with the approved delivery and servicing plan unless otherwise agreed in writing by the local planning authority.

 

14.            Prior to the commencement of development in a phase, details of a scheme of surface water drainage to serve that phase shall be submitted to and approved in writing by the local planning authority. The development in that phase shall thereafter be implemented in accordance with the approved surface water drainage scheme and shall not be occupied until the approved surface water drainage scheme has been full laid out and completed.

 

15.            No development shall commence on any phase until impact studies on the existing water supply infrastructure relating to that phase, which shall determine the magnitude and timing of any new additional capacity required in the system and a suitable connection point, has been submitted to and approved in writing by the Local Planning Authority.

 

16.            Development shall not commence on any phase until a drainage strategy detailing any on and/or off site drainage works for that phase has been submitted to and approved by, the local planning authority in consultation with the sewerage undertaker. No discharge of foul or surface water from the site shall be accepted into the public system until the drainage works referred to in the strategy have been completed.

 

17.            Prior to the commencement of development on a phase, a professional archaeological organisation acceptable to the Local Planning Authority shall prepare an Archaeological Written Scheme of Investigation for that phase which shall be submitted to and approved in writing by the Local Planning Authority.

 

18.            Following the approval of the Written Scheme of Investigation referred to in condition 17, and prior to the commencement of development in a phase (other than in accordance with the agreed Written Scheme of Investigation), a staged programme of archaeological evaluation and mitigation shall be carried out in that phase by the commissioned archaeological organisation in accordance with the approved Written Scheme of Investigation. The programme of work shall include all processing, research and analysis necessary to produce an accessible and useable archive and a full report for publication which shall be submitted to the Local Planning Authority.

 

19.            The development hereby approved shall be carried out at all times in accordance with the methodology contained within the submitted “Archaeological Protection Measures Report – produced by Brian Hamill and dated 19th January 2017” unless otherwise with the prior written agreement of the local planning authority.

 

20.            The development on Phase 1A shall only be used only for purposes falling within Use Class C1 as specified in the Schedule to the Town and Country Planning (Use Classes) ( (England) Order 1987 (as amended) and for no other purpose(s) whatsoever notwithstanding any provisions otherwise contained within the Town and Country Planning (General Permitted Development) (England) Order 2015 (including any  amendments or re-enactments of this Order). The development on Phase 1B shall only be used only for purposes falling within Use Class B1 as specified in the Schedule to the Town and Country Planning (Use Classes) (England) Order 1987 (as amended) and for no other purpose whatsoever notwithstanding any provisions otherwise contained within the Town and Country Planning (General Permitted Development) (England) Order 2015 (including any  amendments or re-enactments of this Order).

 

21.            All applications for reserved matters approval relating to a phase shall be accompanied by details of the external lighting to be installed within that phase including details of luminance and light spillage. The development shall thereafter only be constructed in accordance with the lighting details approved as part of the grant of reserved matters approval and no other external lighting thereafter installed without the prior written consent of the local planning authority.

 

22.            No removal of hedgerows, trees or shrubs shall take place between the 1st March and 31st August inclusive, unless the Local Planning Authority has confirmed in writing that such works can proceed, based on health and safety reasons in the case of a dangerous tree, or the submission of a recent survey (no older than one month) that has been undertaken by a competent ecologist to assess the nesting bird activity on site, together with details of measures to protect the nesting bird interest on the site.

 

23.            All applications for reserved matters approval shall be accompanied by a statement that appraisals the ecological implications of those reserved matters proposals including  how they would mitigate harm to protected/priority species and contribute towards achieving an overall net gain for biodiversity as part of the overall development. Thereafter, measures set out in the statement shall be implemented in full on site in accordance with the details approved as part of the grant of reserved matters approval.

 

24.            If the development on Phase 1A or Phase1B does not commence within three years of the date of this decision, updated surveys for all statutorily protected species assessed as part of the planning application shall be re-undertaken prior to the commencement of the development in order to establish changes in the presence, abundance and impact on such species. The survey results, together with any necessary changes to the mitigation plan or method statement shall be submitted to and approved in writing the Local Planning Authority prior to the commencement of any development on that phase. Thereafter, the development shall be carried out in accordance with the approved details.

 

25.            All buildings hereby approved shall be constructed to achieve at least a BREEAM ‘Very Good’ rating based on the relevant BREEAM standard for that building type applicable at the time of the decision. All applications for reserved matters approval relating to a phase shall be accompanied by details demonstrating how the buildings within that phase would be designed to achieve the BREEAM ‘Very Good’ rating.

 

26.            The first application for reserved matters approval relating to each of Phases 1A and 1B shall be accompanied by an Energy Statement relating to that phase that demonstrates the significant on-site renewable energy provision that will be incorporated into the development on that phase except where such on-site renewable energy provision is robustly demonstrated within the Energy Statement to be unfeasible or unviable. The on-site renewable energy provision approved as part of the reserved matters approval shall thereafter be fully incorporated within the development and no occupation of development within that phase shall take place until the approved on-site renewable energy provision is fully installed and operational.

 

27.            No development shall commence on a phase until full details of the 3m wide combined footway/cycleway (including lighting) along the A41 to serve that phase has been submitted to and approved in writing by the local planning authority. The approved combined footway/cycleway shall thereafter be provided to serve that phase prior to the first occupation of any development within that phase.

 

28.            No development shall take place until full details of the provision of a new bus stop layby along the southbound carriageway of the A41 (adjacent to Phase 1A) have been submitted to and approved in writing by the local planning authority. No development shall thereafter be occupied until the bus stop layby has been provided in accordance with the approved details.

 

29.            No development shall take place until full details of a signalised pedestrian crossing (between the new southbound and existing northbound bus stops of the A41 in the immediate vicinity of the site) has been submitted to and approved in writing by the local planning authority. No occupation of any part of the development shall occur until the approved signalised pedestrian crossing has been provided in accordance with the approved details.

 

30.            No development shall take place on Phase 1B until full details of a new mini-roundabout system to replace the existing Vendee Drive/Wendlebury Road priority junction have been submitted to and approved in writing by the local planning authority. No occupation of development on Phase 1B shall take place until the approved mini-roundabout system has been completed.

 

31.            Unless otherwise agreed in writing by the local planning authority, no development shall be occupied on Phase 1B until the works to the highway shown in drawing no. 35172/5502/008 (contained in the Transport Assessment) have been carried.

 

32.            Development shall not be occupied on Phase 1B unless and until Oxfordshire County Council as the Local Highway Authority has made a Traffic Regulation Order introducing a speed limit reduction to 30mph along the length of Wendlebury Road adjacent to the application site.

 

33.            All applications for reserved matters approval relating to Phase 1B shall be accompanied by details of the proposed alignment and treatment of public footpath 161/8/20 within the site unless the local planning authority has confirmed in writing beforehand that such details are not required for that reserved matters application. The development shall thereafter be carried out in accordance with the public footpath details approved as part of the grant of reserved matters approval.

 

 