Agenda item


Buildings 485, 488 And Land Surrounding Those Buildings (Dorchester Phase 6), Heyford Park, Camp Road, Upper Heyford

Decision:

Approved, subject to various requirements to be set out in the Minutes

Minutes:

The Committee considered application 16/00263/F for the demolition of buildings 485 and 488 and the erection of 43 dwellings with associated parking, infrastructure, landscaping and public open space at Buildings 485, 488 And Land Surrounding Those Buildings (Dorchester Phase 6), Heyford Park, Camp Road, Upper Heyford for Dorchester Group.

 

Gavin Angell, agent for the applicant, addressed the Committee in support of the application.

 

In reaching their decision, the Committee considered the officers’ report and presentation and the address of the public speaker.

 

Resolved

 

That application 16/00263/F be approved, subject to:

 

a)    The applicant entering into a legal agreement linking this permission to the existing obligations secured in the agreement accompanying permission 10/01642/OUT

b)    The following conditions:

 

1          Except where otherwise stipulated by condition, the application shall be carried out strictly in accordance with the following documents: Application forms , Planning, Heritage and Design Statement, Aboricultural Impact assessment and Protection Plan, Construction Specification, Bat Survey and Flooding Risk and Drainage Assessment, and drawings numbered:

                                    Location Plan                       0521 PH6 101

                                    External Works Layout        0521 PH6 104-Rev H

                                    Planning Layout      0521 PH6 102 Rev H

                                    Adoption Plan          0521 PH6 107 Rev G

                                    Tracking Layout 1 of 2        0521 PH6 105 Rev G

                                    Materials Layout       0521 PH6 108 Rev G

                                    Refuse Plan             0521 PH6 111 Ref G

                                    Detailed Planting Proposals 1 of 2           1619 A2 01 I

                                    Detailed Planting Proposals 2 of 2           1619 A2 02 I

                                    Housetype booklet   0521 PH6 HTB Issue 6

                                   

 2         The development to which this permission relates shall be begun not later than the expiration of three years beginning with the date of this permission.

                       

 3         None of the buildings which are the subject of this consent shall be demolished until a contract has been let for the redevelopment of the site in accordance with the granting of a planning permission for such redevelopment.

           

 4         Prior to any demolition on the site, the commencement of the development and any archaeological investigation, a professional archaeological organisation/building recorder acceptable to the Local Planning Authority shall carry out a full recording of the building concerned and submit the completed record to the Local Planning Authority.

           

 5         No materials other than those as shown on plan No. 0521 PH6 108 Rev G are to be used in the new development. There shall be no variation of these materials without the prior written consent of the Local Planning Authority. The development shall be carried out in accordance with the approved schedule.

                       

 6         All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in accordance with BS 4428:1989 Code of Practice for general landscape operations (excluding hard surfaces), or the most up to date and current British Standard, in the first planting and seeding seasons following the occupation of the building(s) or on the completion of the development, whichever is the sooner. Any trees, herbaceous planting and shrubs which, within a period of five years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the current/next planting season with others of similar size and species.

                       

 7         All agreed service trenches, pipe runs, drains or any other excavation to be constructed within the agreed Root Protection Area (RPA) of the tree/trees on the site shall be undertaken in accordance with National Joint Utility Group 'Guidelines for the Planning, Installation and Maintenance of Utility apparatus in Proximity to Trees - Volume 4 and all subsequent revisions and amendments thereof.

                       

 8         Prior to the commencement of the development hereby approved, and notwithstanding the submitted details, full details, locations, specifications and construction methods for all purpose built tree pits and associated above ground features, to include specifications for the installation of below ground, load-bearing 'cell structured' root trenches, root barriers, irrigation systems and a stated volume of a suitable growing medium to facilitate and promote the healthy development of the proposed trees, shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development shall be carried out in accordance with the approved details and specifications.

                                

 9         That all enclosures along all boundaries of the site shall be as shown on the approved plans and such means of enclosure shall be erected prior to the occupation of any dwelling.

                                               

 

10        That before the development is first occupied, the parking, garaging and manoeuvring areas shall be provided in accordance with the plans 0521 PH4 5B 104-1 and 2 hereby approved and shall be constructed, laid out, surfaced, drained and completed in accordance with specification details to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of development, and shall be retained unobstructed except for the parking and manoeuvring of vehicles at all times thereafter

 

11        Prior to the first occupation of any of the dwellings hereby approved, all of the estate roads, footpaths (except for the final surfacing thereof) and parking shall be laid out, constructed, lit and drained in accordance with Oxfordshire County Council's 'Conditions and Specifications for the Construction of Roads' and its subsequent amendments.

                                   

12        Prior to first occupation of any dwelling hereby approved, a Travel Information Pack shall be submitted to and approved by the Local Planning Authority. The first residents of each dwelling shall be provided with a copy of the approved Travel Information Pack.

                       

13        Prior to the commencement of the development hereby approved, and notwithstanding the application details, full details of refuse, fire tender and pantechnicon turning within the site shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the development shall be carried out in accordance with the approved details.

                       

14        The development permitted by this planning permission shall be carried out in accordance with the approved Flood Risk Assessment (FRA) OCT 2010 Waterman and update in March 2016 Woods Hardwick (Ref: 16871 REV 2) by and the following mitigation measures detailed within the FRA:

            o          Limiting the surface water run-off generated by the 1 in 100 year + 30% allowance for Climate Change critical storm so that it will not exceed the run-off over the existing situation and not increase the risk of flooding off-site.

            o          Underground Storage tanks and oversized pipes. (As shown on drawing HEYF- 5-936C and para 6.3.1 of FRA update)

            The mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the timing / phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority.

           

15        Prior to commencement of the development the Applicant shall submit to the Local Planning Authority a SUDS Maintenance and Management Plan for the development. This will include:

           

            o          A maintenance schedule, A site plan showing location of SUDS features and details, Maintenance areas, and Outfalls. Responsibility for the management and maintenance of each element of the SUDS scheme will be detailed within the Management Plan and a health and safety plan where risks are involved in the maintenance activity will be required.

 

16        Prior to commencement of the development the Applicant shall submit to the Local Planning Authority a revised Flood Route and Storage Plan for exceedance flows at the site:

            o          To update the existing drawing 'Surface Water Drainage Overview - Residual Flooding' Drawing Number HEYF /5/148C to reflect any revised microsimulation modelling results, as built constructed site changes, and changes to exceedance storage areas.

           

17        Prior to the commencement of the development hereby approved, full details of the fire hydrants to be provided or enhanced on the site shall be submitted to and approved in writing by the Local Planning Authority. Thereafter and prior to the first occupation of the development, the fire hydrants shall be provided or enhanced in accordance with the approved details and retained as such thereafter.

 

18        If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted a remediation strategy to the local planning authority detailing how this unsuspected contamination shall be dealt with and obtained written approval from the local planning authority. The remediation strategy shall be implemented as approved.

 

19        Prior to the first occupation of the development hereby approved, a Landscape and Ecology Management Plan (LEMP) shall be submitted to and approved in writing by the Local Planning Authority. Thereafter, the LEMP shall be carried out in accordance with the approved details.

                       

 

 

 

 