Relocation of CDC administrative headquarters from Bodicote House to Castle Quay
Exempt report of Assistant Director Property
Additional documents:
Decision:
Recommendation agreed as set out in the exempt report
Minutes:
The Assistant Director Property submitted an exempt report which sought approval of additional budget to meet a project overspend on the Castle Quay Office project. The increased capital budget requested was £645,800.
Resolved
(1) That the forecast overspend be noted and an increase in the Capital Programme of £645,800 towards the delivery of Castle Quay relocation of offices project be approved in order to authorise expenditure for the project.