Issue - meetings


Kelberg Ltd, Northampton Road, Weston On The Green, Bicester, OX25 3TH

Meeting: 11/07/2024 - Planning Committee (Item 32)

32 Kelberg Ltd, Northampton Road, Weston On The Green, Bicester, OX25 3TH pdf icon PDF 1 MB

Additional documents:

Decision:

Approved in line with officer recommendation, subject to no objection from the arboricultural officer and subject to conditions. Details to be set out in the minutes.

Minutes:

The Committee considered application 24/00893/F for the proposed erection of 8-bay workshop and associated works at Kelberg Ltd, Northampton Road, Weston On The Green, Bicester, OX25 3TH for Kelberg Trailers And Trucks Ltd.

 

In reaching its decision the Committee considered the officers report and  presentation.

 

Resolved

 

That, in line with the officer’s recommendation, application 24/00893/F be delegated to the Assistant Director for Planning and Development to grant permission subject to:

 

·         No objections from the Arboricultural Officer and

·         The conditions set out below (and any amendments to those conditions as deemed necessary)

 

Conditions

 

Time Limit

 

1.         The development to which this permission relates shall be begun not later than the expiration of three years beginning with the date of this permission.

 

Reason - To comply with the provisions of Section 91 of the Town and Country Planning Act 1990, as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.

 

Compliance with Plans

 

2.         Except where otherwise stipulated by conditions attached to this permission, the development shall be carried out strictly in accordance with the following plans and documents: unnumbered location/site plan (submitted 2.4.2024) and drawing number 2024-728-20.

 

Reason – For the avoidance of doubt, to ensure that the development is carried out only as approved by the Local Planning Authority and comply with Government guidance contained within the National Planning Policy Framework.

 

3.         Development shall not commence until a construction management strategy has been submitted to and approved in writing by the Local Planning Authority covering the application site and any adjoining land which will be used during the construction period. Such a strategy shall include the details of cranes and other tall construction equipment (including the details of obstacle lighting). The approved strategy (or any variation approved in writing by the Local Planning Authority) shall be implemented for the duration of the construction period.

 

Reason – To ensure that construction work and construction equipment on the site and adjoining land does not obstruct air traffic movements or otherwise impede the effective operation of air traffic navigation transmitter/receiver systems and in accordance with Government guidance contained within the National Planning Policy Framework.

 

4.         Before any above ground works commence a scheme for the provision and implementation of surface water drainage shall be submitted to and approved in writing by the Local Planning Authority. The drainage works shall be constructed and completed in accordance with the approved plans before the first use of the building hereby approved and shall be maintained as such thereafter.

 

Reason - To ensure satisfactory drainage of the site in the interests of achieving sustainable development, public health, to avoid flooding of adjacent land and property to comply with Policy ESD6 of the Cherwell Local Plan 2011-2031 Part 1, saved Policy ENV1 of the Cherwell Local Plan 1996 and Government guidance contained within the National Planning Policy Framework.

 

5.         A method statement for enhancing the site for biodiversity shall be submitted to and approved in writing by the Local Planning Authority prior to the  ...  view the full minutes text for item 32