Purpose of report
This report seeks approval of the Business Case to commence work on the project of relocating the Council’s administrative headquarters from Bodicote House to Castle Quay
Recommendations
The meeting is recommended:
1.1 To approve the Business Case for the relocation of the Council Offices from Bodicote House to Castle Quay.
1.2 To delegate authority to the Corporate Director of Resources, in consultation with the Portfolio Holder for Property, to initiate a project to relocate the administrative offices of the Council to Castle Quay
1.3 To recommend to the Council to approve an increase in the Capital Programme of £4.5m towards the delivery of this project in order to authorise expenditure for the project
Additional documents:
Decision:
Resolved
(1) That the Business Case for the relocation of the Council Offices from Bodicote House to Castle Quay be approved.
(2) That authority be delegated to the Corporate Director of Resources, in consultation with the Portfolio Holder for Property, to initiate a project to relocate the administrative offices of the Council to Castle Quay
(3) That Council be recommended to approve an increase in the Capital Programme of £4.5m towards the delivery of this project in order to authorise expenditure for the project
Minutes:
The press and public having been readmitted to the meeting and the recommendations proposed and seconded, the Chairman moved to the vote.
Resolved
(1) That the Business Case for the relocation of the Council Offices from Bodicote House to Castle Quay be approved.
(2) That authority be delegated to the Corporate Director of Resources, in consultation with the Portfolio Holder for Property, to initiate a project to relocate the administrative offices of the Council to Castle Quay
(3) That Council be recommended to approve an increase in the Capital Programme of £4.5m towards the delivery of this project in order to authorise expenditure for the project
Reasons
The Council has reviewed the existing office provision over a number of years, cumulating with this final review. It has been ascertained that the most economically advantageous provision of office accommodation would be to relocate to the Castle Quay Shopping Centre. Whilst this is financially the most appropriate provision of accommodation, it also aligns to the aspirations of creating a multi-use hub at Castle Quay, acting as a catalyst for the regeneration of Banbury Town Centre. The option also has the potential to redevelop the current Bodicote House site (separate decision) and works towards the Council’s environmental aspirations in enabling a more efficient office environment with greater public transport connectivity to the site
Alternative options
A number of alternative options were considered and deemed to be less favourable than the recommendation herein, particularly from a financial perspective; these options and reasons for rejection are detailed at length in the exempt Business Case.