The Committee considered application 18/00091/F for 14,200 sq m of logistics floor space, within class B8, including ancillary class B1 (a) offices (929 sq m), erection of security gatehouse, security fence, sprinkler tank and pump house, with an access road and associated site infrastructure including external service yard, lorry parking, landscaping, amenity open space including 10m green corridor with 3m foot path and cycle link to wider Bicester 12 and storm water drainage infrastructure and private sewage treatment plant at Symmetry Park, Aylesbury Road A41, Ambrosden for Db Symmetry (Bicester Reid) Ltd.

 

John Broad, on behalf of CPRE, addressed the committee in objection to the application.

 

Louise Steele, agent for the applicant, addressed the committee in support of the application.

 

In reaching their decision, the committee considered the officers’ report, presentation and written update.

 

Resolved

 

That application 18/00091/F be approved and that authority be delegated to the Interim Director for Planning and Regeneration to grant permission subject to:

 

I.        the applicant entering into an appropriate legal agreement

 

II.        notification of decision to planning casework unit as it is EIA development and;

 

III.        the following conditions (and any amendments to the content and final wording of those conditions as deemed necessary):

 

1.               The development to which this permission relates shall be begun not later than the expiration of three years beginning with the date of this permission.        

 

2.               Except where otherwise stipulated by condition, the development shall be carried out strictly in accordance with the following plans and documents: Application forms, FRA dared December 2015 prepared by Peter Brett Associates and additional technical notes prepared by Hydrock dated march 2018 revision D.; Archaeological Evaluation Report MK 050/16 by CFA Archaeology Ltd; Design and Access Statement dated January 2018 by PHP Architects; Planning Statement dated January 2018; Biodiversity Method Statement and Management Plan dated March 2017 EDP2606-20d, Energy Statement dated September 2016 by Peter Brett Associates, Phase II Ground Investigation report dated May 2016 16.02.026; Environmental Statement dated January 2018 PF/9932; Transport Assessment dated April 2016 by Peter Brett Associates; Framework Travel Plan dated December 2016 by Peter Brett Associates and drawing numbers: 4036-B09-011 rev PO3 - Location Plan; 4036-B09-000 Rev PO5 Red Line Plan; 4036-B09-014 rev PO8- Parking details; 4036-B09-001 rev P20-Indicative site masterplan; 4036-B09-013 rev PO8-Fencing details; 4036-B09-008 rev P15-Site layout plan; EDP-2606-123i; 124k; 125i; 126i; 127j; 129c and 128i Soft Landscape Scheme sheets 1-7; 4036-B09-020 Rev PO6 Site Sections; EDP2606/50L illustrative ecology and landscape plan; 4036-BO9-006 Rev PO6; 4036-B09-009 Rev P05-elevations and sections; 4036-B09-012 Rev P01-Gatehouse details; 4036-B09-015 Rev P01-Roof plan; 4036-B09-016 Rev P04-Parameter line comparison plan; 4036-B09-017 P03-Sprinkler installation; 4036-015 rev P20-Parameters plan; Drainage Plans by Hydrock: SYM-HYD-XX-XX-DR-C-0001 Rev P3; 0002 rev P3; 0003 Rev P2; 0004 Rev P1; 0005 Rev P3; 0006 Rev P1; 0007 Rev P1; 0120 rev P2; 0105 rev T2 and 0104 Rev T2 and vehicle tracking shhets 0009 P2; 0010 P3 and 0011.

           

3.               Prior to the commencement of the development hereby approved, full details of the external lighting shall be submitted  ...  view the full minutes text for item 13