Agenda and minutes


Accounts, Audit and Risk Committee - Wednesday 24 June 2015 6.30 pm

Venue: Bodicote House, Bodicote, Banbury, OX15 4AA

Contact: James Doble, Democratic and Elections  Email: james.doble@cherwellandsouthnorthants.gov.uk, 01295 221587

Items
No. Item

3.

Declarations of Interest

Members are asked to declare any interest and the nature of that interest which they may have in any of the items under consideration at this meeting.

Minutes:

There were no declarations of interest.

4.

Petitions and Requests to Address the Meeting

The Chairman to report on any requests to submit petitions or to address the meeting.

Minutes:

There were no petitions or requests to address the meeting.

5.

Urgent Business

The Chairman to advise whether they have agreed to any item of urgent business being admitted to the agenda.

 

Minutes:

There was no urgent business.

6.

Minutes pdf icon PDF 205 KB

To confirm as a correct record the Minutes of the meetings of the Committee held on 26 March 2015 and 19 May 2015.

Additional documents:

Minutes:

The minutes of the meetings of the Committee held on 26 March 2015 and 19 May 2015 were agreed as a correct record and signed by the Chairman.

7.

Chairman's Announcements

To receive communications from the Chairman.

Minutes:

The Chairman reminded Councillors that filming and broadcasting of the meeting was permitted, subject to the efficient running of the meeting not being affected.

 

8.

External Audit Progress Report pdf icon PDF 119 KB

Report of the Head of Finance and Procurement

 

Purpose of report

 

To receive Ernst Young’s Audit Fee Letter 2015-16 and to receive a verbal update of progress to date for 2014-15.

 

Recommendations

            

The meeting is recommended to:

 

1.1       Note the Audit Fee Letter and the progress update from Ernst Young.

Additional documents:

Minutes:

Mark Surridge, Ernst Young, the council’s external auditor, introduced the Audit Fee Letter 2015-16 and gave a verbal update on progress to date for 2014-15. It was noted that the audit fee would be 25% lower following a national procurement exercise.

 

In the course of discussion it was noted that whilst the total figure quoted in the letter was correct, the individual figures did not add up to the total.

 

Resolved

 

(1)          That the Audit Fee Letter and the progress update from Ernst Young be noted.

 

9.

Internal Audit Progress Report and Annual Plan pdf icon PDF 203 KB

Report of the Head of Finance and Procurement

 

Purpose of report

 

To receive the PwC Internal Audit Annual Report.

 

Recommendations

            

The meeting is recommended to:

 

1.1       Consider and note the contents of the Annual Report.

Additional documents:

Minutes:

Ed Cook, PwC, the council’s internal auditor, introduced the Internal Audit Annual Report. It was noted that whilst the council was ranked as ‘improvement required’, this was the second highest category, with the highest being ‘adequate’.

 

Resolved

 

(1)          That the Internal Audit Annual Report be noted.

 

10.

Corporate Risk Register Annual Report pdf icon PDF 264 KB

Report of Head of Transformation and Corporate Performance Manager

 

Purpose of report  

 

To update the Committee on the management of Strategic, Corporate and Partnership Risks during the fourth and final quarter of 2014/15 and to report the progress made on the 2015/16 Risk & Opportunities Management Strategy review, Risk Training programme and Internal Audit review.

 

Recommendations

            

The meeting is recommended to:

 

1.1      review the quarter 4 Strategic, Corporate and Partnership Risk Register and identify any issues for further consideration.

 

1.2      note that there have been changes to three of the risk scores, one of which is CDC

            specific, the other two are joint risks across both councils.

 

1.3      note that three risks have been closed since the last meeting; two of which are CDC specific, one is a joint risk across both councils.

 

1.4      note that one new joint strategic risk has been added to the register since the last meeting.

 

1.5      note the progress made on the 2015/16 Risk and Opportunities Management Strategy review, the 2015/16 Risk Training Programme and the 2014/15 Risk Audit

 

Additional documents:

Minutes:

The Acting Corporate Performance Manager, submitted a report to update the Committee on the management of Strategic, Corporate and Partnership Risks during the fourth and final quarter of 2014/15 and to report the progress made on the 2015/16 Risk & Opportunities Management Strategy review, Risk Training programme and Internal Audit review.

 

The Committee noted that there had been a decrease in the residual risk with regard to Joint Working (three-way) and the Dry Recycling Contract, however both issues were likely to change and risk would be reassessed as required.

 

In the course of discussion it was queried whether Bicester Gateway had been identified as a risk duty to the potential impact on Pioneer Square in terms of lost trade and revenue. The Acting Corporate Performance Manager agreed to clarify this with the Commercial Director (Bicester).

            

Resolved

 

(1)          That the quarter 4 Strategic, Corporate and Partnership Risk Register be noted.

 

(2)          That it be noted that there had been changes to three of the risk scores, one of which was Cherwell District Council (CDC) specific, the other two were joint risks across both councils.

 

(3)          That it be noted that three risks have been closed since the last meeting; two of which are CDC specific, one is a joint risk across both CDC and South Northamptonshire Council.

 

(4)          That it be noted that one new joint strategic risk had been added to the register since the last meeting.

 

(5)          That the progress made on the 2015/16 Risk and Opportunities Management Strategy review, the 2015/16 Risk Training Programme and the 2014/15 Risk Audit be noted.

 

 

11.

Q4 Treasury Management Report pdf icon PDF 236 KB

Report of Head of Finance and Procurement

 

Purpose of report

 

To receive information on treasury management performance and compliance with treasury management policy for 2014-15 for Quarter 4 ending 31 March 2015 as required by the Treasury Management Code of Practice.

 

Recommendations

            

The meeting is recommended:

 

1.1         To note the contents of the Quarter 4 (Q4) Treasury Report

 

Minutes:

The Head of Finance and Procurement submitted a report providing information on treasury management performance and compliance with treasury management policy for 2014-15 for Quarter 4 ending 31 March 2015 as required by the Treasury Management Code of Practice, in considering the report members noted the exempt appendix.

 

In the course of discussion members expressed concern regarding the amount of capital slippage where no spend had occurred. It was agreed that it would be appropriate to refer the retrospective issue of capital slippage in 2014/15 to the Overview and Scrutiny for them to investigate why this had not occurred and if there were issues with either the management of services or problems with business planning where staff time for capital schemes should be allocated.

 

It was also agreed that there should be a referral to the Budget Planning Committee to enable them to consider procedures to monitor capital spend in year and so that measures can be taken at the budget planning stage so that in future only those schemes where there are resources to deliver the scheme are approved.

 

Resolved

            

(1)          That the contents of the Quarter 4 (Q4) Treasury Report be noted.

 

(2)          That a referral be made to the Overview and Scrutiny Committee requesting the Committee investigate the retrospective issue of capital slippage where no spend had occurred and if there were issues with either the management of services or problems with business planning where staff time for capital schemes should be allocated

 

(3)          That a referral be made to the Budget Planning Committee to request they consider procedures to monitor capital spend in year so that measures could be taken at the budget planning stage so that in future only those schemes where there were resources to deliver the scheme were approved.

 

 

12.

Statement of Accounts Review pdf icon PDF 120 KB

** Appendix 3 to this report will follow as it is currently being reviewed and finalised **

 

Report of the Head of Finance and Procurement

 

Purpose of report

 

The purpose of this report is for members to consider and endorse the pre-audit Statement of Accounts for 2014-15.

 

Recommendations

            

The meeting is recommended to:

 

1.1         Approve the carry forward of budget underspends from 2014-2015 to 2015-2016 as detailed in Appendix 1.

 

1.2         Approve the balances on capital schemes which have slipped in 2014-2015 to be carried forward into the 2015-2016 capital programme as set out in Appendix 2.

 

1.3         Consider the Statement of Accounts set out in Appendix 3 (to follow).

 

1.4         Note the outcomes from the informal review undertaken on 25 June immediately prior to the formal meeting at 5.00pm which will be updated verbally at the meeting

Additional documents:

Minutes:

The Head of Finance and Procurement submitted a report for members to consider and endorse the pre-audit Statement of Accounts for 2014-15.

 

Resolved

 

(1)          That the carry forward of budget underspends from 2014-2015 to 2015-2016 (annex to the minutes as set out in the minute book) be approved.

 

(2)          That the balances on capital schemes which have slipped in 2014-2015 to be carried forward into the 2015-2016 capital programme (annex to the minutes as set out in the minute book) be approved.

 

(3)          That the Statement of Accounts be noted.

 

(4)          That the outcomes from the informal review undertaken on 25 June immediately prior to the formal meeting at 5.00pm be noted.

 

13.

Annual Governance Statement 2014-15 pdf icon PDF 112 KB

Report of Head of Finance and Procurement

 

Purpose of report

 

To report the Annual Governance Statement.  The Annual Governance Statement will be considered at the same time as the Statement of Accounts for 2014/15. 

 

Recommendations

            

The Committee is recommended to:

 

1.1       Consider and endorse the Annual Governance Statement 2014-15 (Appendix 1).

 

Additional documents:

Minutes:

The Head of Finance and Procurement submitted the Annual Governance Statement to the meeting. In the course of discussion members agreed that reference to the Budget Planning Committee should be included within the description of the governance framework.

 

Resolved

 

(1)          That the Annual Governance Statement 2014-15 be endorsed with reference to the Budget Planning Committee should be included within the description of the governance framework.